Power rental

Temporary power rental: what to rent, what to ask and how to get quotes

Rent a commercial temporary power package (a mobile generator plus distribution panels, cam-lok cable, transformers, a transfer switch and fuel) for a planned shutdown, an equipment failure, a construction job or an event. For an accurate quote, providers need your voltage and phase, your load in amps or kW, your dates and runtime, and where the unit will connect. Critical Power Index doesn't rent equipment: size your load below, then send one request and we'll try to match it with up to three independent providers that list temporary power rental in your area.

Updated · How we research

What a temporary power package includes

A temporary power rental is rarely just a generator. Rental fleets supply the generator together with the gear that gets its output safely to your loads: distribution, cable, transformers, transfer switches and fuel storage.13 Which pieces you need depends on how the power will reach your equipment.

Common temporary power rental components and ratings listed by US rental fleets (checked November 2026; ratings vary by provider and location)
ComponentWhat it doesRatings fleets list
Mobile generatorProduces power, usually diesel, on a trailer or skidAbout 13 kW to 1,600 kW towable diesel in one fleet6; a manufacturer's rental network lists 16 kW to 500 kW mobile units8
Distribution panelSplits generator output into breaker-protected feeders50 A, 600 A and 800 A panels in one fleet3
Spider boxPortable box with receptacles for tools, lighting and small loadsOften a mix of twist-lock and 120 V duplex receptacles2
Cam-lok cableSingle-conductor cable with quick connectors between generator, panels and buildingLength set by the distance from the generator to the connection point2; size and count depend on your load current
TransformerSteps voltage up or down to match equipmentStep-up, step-down and multi-tap medium-voltage units1; one fleet lists units up to 6,300 kVA and 25 kV10
Automatic transfer switch (ATS)Moves load to the generator when the normal source fails200 A, 120 to 600 V with cam-lok input and output in one fleet4; 200 A to 4,000 A options in another5
Fuel tankExtends runtime between deliveriesSee fuel and runtime

For loads beyond a single trailer, fleets run units in parallel. One national fleet says its 200 kW to 500 kW units are built with parallel systems1, and another lists containerized 2 MW generators.9 If you mainly need a different voltage from a source you already have, start with rental transformers instead.

When facilities rent temporary power

Common reasons to rent include planned shutdowns, equipment failures, construction, events and testing. One generator manufacturer's rental program lists events, construction sites, telecom networks, planned maintenance outages and emergency response.8

Planned shutdowns

Switchgear, transformer or bus work often means de-energizing part of a building. A rented generator and distribution can carry critical loads during switchgear maintenance and testing. One fleet markets its 600 A panel for industrial plant shutdowns and maintenance.3

Failures and outages

When a standby generator, transformer or utility feed fails, a rental can bridge the gap while the permanent gear is fixed. If your own generator is the problem, pair the rental with industrial generator repair. If a facility-owned transformer failed, a rental transformer matched to the failed unit can carry the load while the failed unit is tested and repaired.

Construction before permanent service

Job sites need power for tools and lighting before the permanent utility service is in place. See the note below on utility temporary service.

Events

Outdoor and temporary events are a standard rental use.89 Noise and cable routing often matter more at events.

Testing and commissioning

Data center and plant commissioning may need temporary power and a measurable load. A fleet that rents load banks says they support Level 4 and Level 5 commissioning tests.21 To rent the equipment, see sizing a rental load bank; to have a crew run and document an NFPA 110 test, see generator load bank testing.

When a rental generator isn't the right fit

For a long construction job, ask your utility early about temporary service or a construction power pole, and plan a rental generator for the gap: one national fleet notes it can take months for a utility to install wiring and poles.1 If you need a small portable generator for a home, start with a local rental store. This page, and the requests we handle, cover commercial and industrial packages.

How to size a rental generator

Start with the load you need to carry. Turn it into kVA and kW, then let the provider add capacity for motor starting and other hard-to-serve loads. If you know the voltage and the current your loads draw (from a panel schedule, a meter reading or the breaker or service rating), the calculator gives the apparent power (kVA) and real power (kW) a generator must supply.

Temporary power sizing calculator

Calculator

Apparent power

–

Real power

–

Load plus your margin

–

Formulas: three-phase kVA = V × A × 1.732 ÷ 1,000; single-phase kVA = V × A ÷ 1,000; kW = kVA × power factor. The planning margin is your own assumption, not a code requirement. Motor starting, UPS and non-linear loads can need a much larger generator; give the provider your load list so they can size for starting current.

The formulas come from generator manufacturers' engineering guides. For three-phase power, kVA = volts × amps × 1.732 ÷ 1,000 and kW = volts × amps × power factor × 1.732 ÷ 1,000, using line-to-line voltage.1112 For single-phase power, Cummins lists kVA = volts × amps ÷ 1,000 and kW = volts × amps × power factor ÷ 1,000.11 Eaton's worked example: 445 A at 480 V is 370 kVA12, which at a 0.8 power factor is about 296 kW.

A breaker or service rating gives the maximum the circuit can carry, not what your equipment actually draws. If you can, give the provider measured demand (a utility interval report or a recorded meter reading) along with a list of large motors, chillers, elevators, UPS systems and variable-frequency drives. Those loads drive generator size more than steady running current does, so ask the provider to size for them.

Is there an "80% rule" for generators?

No code we found requires running a generator at 80% of its rating; that figure is a rule of thumb. You'll also see "80%" used for breakers and conductors that carry continuous loads. That's an electrical-code question your electrician handles when sizing the feeders, not a generator rating.

The generator limits that do exist sit in each manufacturer's rating definitions. Cummins says the prime rating applies when a generator supplies power in lieu of commercially purchased power, and the standby rating only where it backs up a reliable utility source.11 Its standby rating assumes variable loads averaging 70% of the rating over 24 hours, for no more than 200 hours a year. For prime ratings in variable-load service, it says the average load shouldn't exceed 70% of the prime rating.11 A rental that replaces utility power for weeks fits the prime definition, so ask which rating the quoted kW refers to.

The calculator's 25% planning margin is an example, not a standard. With it, the generator would run at about 80% of the figure the calculator shows. Keeping average load at 70% of a rating takes a margin of about 43%, so change the margin to match your provider's advice.

Oversizing has its own cost. Cummins warns that low combustion temperature can increase soot and fouling of exhaust aftertreatment, and that "wet stacking" can deposit unburnt fuel in the exhaust system.13 If your real load will be a small fraction of the unit's rating, ask the provider how they'll handle it.

What drives the cost of a rental

The total depends on much more than the generator's rate. We couldn't find a credible national price list, so this page doesn't publish prices. Expect a quote to separate these items:

  • Equipment size and count: generator kW, number of panels, spider boxes and transformers, and whether units are paralleled.
  • Rental period: daily, weekly and monthly rates differ; ask how idle standby time is billed.
  • Delivery and pickup: distance from the branch, crane or forklift needs, and after-hours delivery.
  • Cable and installation labor: cable length from the generator pad to the connection point, and whether the provider or your electrician makes the tie-in.
  • Fuel and DEF: first fill, refueling trips, and how fuel is priced.
  • Options: sound-attenuated enclosures, remote monitoring, an on-site operator, spill containment.
  • Urgency: an emergency rental after a failure leaves less room to compare than a shutdown booked weeks ahead.

How much does it cost to rent a generator for a day?

We can't give a reliable national figure. When we checked in November 2026, United Rentals and Sunbelt Rentals showed rental rates only after you set a job location.35 For a commercial unit, the day rate is also only part of the bill: delivery, cable, connection labor and fuel add to it, so compare full quotes rather than rates.

Companies named on this page are cited as public sources for their published fleet data. Critical Power Index has no partnership or referral agreement with them, and naming them doesn't mean they're in our referral network, will receive your request, or endorse this site.

Is it cheaper to rent or buy a generator?

Renting generally fits needs measured in days or months, because you avoid buying, storing, maintaining and testing a unit. We couldn't find published national prices to compare, so price both for your case. For permanent backup, a facility usually buys and installs a stationary standby system, which falls under different emissions rules. If you rent for every storm season or shutdown, compare a docking station plus repeat rentals against owning, and check the 12-month location rule in the emissions section if a portable unit would stay put.

How the rental connects to your building

How the generator ties in decides much of the labor in the quote. If the building has a pre-installed cam-lok connection cabinet, often called a docking station, the rental cables plug straight into it. Without one, a licensed electrician often has to make a temporary connection to the generator power cables.2

  • Docking station or generator connection cabinet. Fastest hookup. It can pay for itself if you rent for every shutdown or storm season; ask an electrician to price one.
  • Temporary tie-in by an electrician. Common for one-time shutdowns and for buildings with no provision. The quote should say who supplies the electrician.
  • Rental transfer switch. When the rental has to pick up load automatically, fleets rent ATS units from 200 A upward45; one lists cam-lok input and output.4
  • Stand-alone distribution. On job sites and at events, the generator feeds panels and spider boxes directly with no building tie-in.23

Also tell the provider where the unit can sit and how far that spot is from the connection point. One generator dealer lists generator location and distance to the electrical connection among its first planning questions.2 Distance sets cable length, which affects voltage drop and cost.

Fuel, runtime and refueling

Runtime depends on load and tank size, so plan fuel for the whole rental, not only the first day. One national fleet estimates a diesel generator uses about 0.4 to 0.8 gallons per hour for every 10 kW it produces, and says a heavy-duty 200 kW unit will likely burn up to 15 gallons per hour.67 The same fleet says generators often carry a 24-hour fuel tank, and some have 48- to 72-hour tanks.6

  • Ask who refuels, how often, and whether fuel is billed at a set price or at market price on delivery.
  • For long rentals, ask about auxiliary tanks and fuel management. One fleet offers scheduled fuel deliveries and remote monitoring as services.9
  • Tier 4 Final units from at least one manufacturer use selective catalytic reduction with diesel exhaust fluid (DEF)14, so the fuel plan should cover DEF as well as diesel.

Do rental generators need to be EPA Tier 4 Final?

Federal rules generally treat portable rental generators as nonroad engines, and rental fleets advertise Tier 4 Final units.914 EPA finalized Tier 4 emission standards for nonroad diesel engines in 2004.15 Under 40 CFR 1068.30, an engine is nonroad if it's portable or transportable. Wheels, skids, a trailer or a platform are signs of that.16

The status has a time limit. A portable engine stops counting as nonroad if it "remains or will remain at a location for more than 12 consecutive months," or a shorter period at a seasonal source.16 If a temporary unit may stay past a year at the same site, raise it with your environmental staff and the provider before you sign. Swapping in a replacement unit that does the same or a similar job doesn't reset the count; the rule adds the replacement's time to the original's.16

Your permanent standby generator may sit under different rules. EPA's stationary engine standard points manufacturers of most 2007-and-later emergency stationary diesel engines of 37 kW and up (other than fire pump engines) to the Tier 2 or Tier 3 nonroad standards, not Tier 4.17 So a site's permanent standby set may be certified to Tier 2 or Tier 3 while the rental parked next to it is Tier 4 Final.

Fleets list Tier 4 Final models across wide size ranges; one says its Tier 4 Final generators run from 25 kW to 1,500 kW.9 We could not confirm a national rule that requires Tier 4 Final for a given site. State and local air rules and project specifications vary, so ask your air agency or project engineer.

Permits, inspection and OSHA rules for temporary wiring

Whether a temporary generator hookup needs an electrical permit or inspection is up to your local authority having jurisdiction (AHJ). We found no single national rule, so call the local building or electrical department before the delivery date, especially for a building tie-in.

  • National Electrical Code. NFPA 70 (the NEC) covers temporary wiring in Article 590, Temporary Installations; an older NFPA 1 excerpt filed in an OSHA docket refers to it.20 Ask your electrician which NEC edition your AHJ enforces and how Article 590 applies to your hookup.
  • OSHA on construction sites. 29 CFR 1926.405(a)(2)(i) allows temporary power and lighting wiring of a class less than a permanent installation would need. All other permanent-wiring rules still apply, and the temporary wiring has to be removed "immediately upon completion of construction or the purpose for which the wiring was installed."18
  • Ground-fault protection. On construction sites, OSHA requires either ground-fault circuit interrupters on 120 V, single-phase, 15 A and 20 A receptacle outlets or an assured equipment grounding conductor program.19 Ask whether the spider boxes supplied include GFCI protection.

How to compare rental providers

Compare quotes on scope, not just the day rate. Two quotes for the "same" 500 kW rental can differ in cable, labor, fuel and who's responsible for the connection. Questions worth asking:

  1. What's included? Generator, distribution, cable, transformer, ATS, fuel, delivery, setup, removal. Get it itemized.
  2. Which rating is the kW? Prime or standby, and at what power factor and voltage.
  3. Who makes the connection? Provider technicians, your electrician or a subcontractor. Who pulls any permit?
  4. What's the emissions tier? Ask for the engine's EPA tier and whether DEF is supplied.
  5. How is fuel handled? Refueling schedule, fuel price basis and spill containment.
  6. What happens if the unit fails? Ask how service calls work, whether a backup unit is available, and whether remote monitoring is included.
  7. How loud is it? Ask for the sound rating and the distance at which it's measured, especially for events or occupied buildings.
  8. What insurance and paperwork do they need from you? Certificates, site access rules and damage waivers.

If the rental supports a shutdown for electrical testing, ask the rental provider to coordinate the cutover with your testing firm.

How a rental works, from request to pickup

This page doesn't give delivery lead times, because they depend on the unit, the branch's inventory and your site. Book a planned shutdown as early as you can, and get the delivery window in writing. Expect these steps:

  1. Request. Send your load, voltage, dates and site details (see the checklist below).
  2. Site check. The provider may visit or ask for photos of the main switchboard, the connection point and the planned generator location.
  3. Quote and scope. Agree in writing on the equipment, who makes the connection, fuel, and delivery and pickup dates.
  4. Permit and inspection. If your AHJ requires one for the hookup, schedule it before the delivery date.
  5. Delivery and setup. Tell the provider about gates, height limits, ground conditions and any crane or forklift access.
  6. Connection and startup. Once the cable is connected, ask for the generator to be started and checked under load before you rely on it.
  7. Refueling. Fuel and DEF deliveries follow the agreed schedule for the length of the rental.
  8. Disconnect and pickup. On construction sites, OSHA requires temporary wiring to be removed once its purpose is complete.18

Larger or paralleled units, crane lifts, permits and building tie-ins each add planning steps, so raise them early. If equipment has already failed and you have a rental account or service contract, call that provider first. Otherwise choose "Urgent: equipment is down now" as your timeline in the quote form so the request is reviewed as urgent. We're a referral service, so we can't promise a response time.

What to send for an accurate quote

A provider can price a rental accurately when you send the electrical basics and the site facts together. This is our own intake checklist. Voltage, unit location and distance to the connection come straight from a provider's planning questions2; the rest are the details providers need to finish the quote.

Temporary power rental quote checklist (Critical Power Index intake list)
ItemExample
Voltage and phase480 V three-phase, 208/120 V three-phase, 240/120 V single-phase
LoadkW or kVA, or amps per phase; peak demand if you have it
Large or sensitive loadsLargest motors (hp), chillers, elevators, UPS, VFDs
ConnectionDocking station, temporary tie-in, ATS needed, or stand-alone distribution
DistributionNumber of panels or spider boxes, receptacle types, transformer needs
Dates and runtimeDelivery and pickup dates; continuous, standby or work-hours operation
LocationSite ZIP code, pad location, distance to the connection point, access limits
FuelDiesel or gas, who refuels, tank size preference
Site rulesEmissions tier, noise limits, permit or inspection requirements

Photos of the main switchboard nameplate and the planned generator location help. Paste the checklist items into the "What do you need?" box when you request quotes. If equipment is down now, choose "Urgent" as your timeline.

Limits of this guide

This page is general information, not engineering advice. Generator sizing for motors, UPS systems and other non-linear loads needs a qualified engineer or the provider's application staff, and the calculator's planning margin is an example, not a recommendation. Electrical code editions, permit rules and air-quality requirements vary by state and local jurisdiction; confirm them with your AHJ and air agency. Fuel use and equipment ranges come from individual providers and change by fleet and location. We could not verify national rental prices or lead times, so this page doesn't publish any. We can't promise that a provider covers every area.

Get quotes through Critical Power Index

Send one request with your load, dates and site details. We review it and, where we can find them, share it with up to three independent providers that list temporary power rental near your ZIP code. They aren't necessarily the companies named on this page. Coverage varies by area. Providers contact you directly, and you decide whether to hire anyone. It's free for facilities. Providers may pay us a referral fee (see the referral disclosure). Critical Power Index is a referral service, not a rental company or electrical contractor. How it works.

Sources

  1. Temporary Jobsite Power for Construction Sites, Sunbelt Rentals. Rental company page: package components, parallel units, transformers, utility timing. Checked 2026-11-26.
  2. Understanding Power Distribution for Rental Generators, Clifford Power Systems, February 12, 2024. Provider page: docking stations, electrician connections, spider boxes, planning questions. Checked 2026-11-26.
  3. Power Distribution Equipment Rentals, United Rentals. Rental company product listings: 50 A, 600 A and 800 A distribution panels; rates shown only after setting a location. Checked 2026-11-26.
  4. Transfer Switch Rentals, United Rentals. Rental company product listing: 200 A ATS, 120 to 600 V, cam-lok input and output. Checked 2026-11-26.
  5. Manual Double Throws and Transfer Switches, Sunbelt Rentals. Rental company listing: ATS options from 200 to 4,000 A; rates shown only after setting a location. Checked 2026-11-26.
  6. Diesel Generator Rentals, United Rentals. Rental company page: 13 kW to 1,600 kW towable range, fuel use per 10 kW, tank runtimes. Checked 2026-11-26.
  7. Generator Rentals, United Rentals. Rental company page: 200 kW fuel consumption estimate. Checked 2026-11-26.
  8. Rental Power, Caterpillar. Manufacturer page: 16 kW to 500 kW mobile generators and common rental uses. Checked 2026-11-26.
  9. Generators, Aggreko. Rental company page: Tier 4 Final 25 kW to 1,500 kW range, containerized units, fuel management and remote monitoring. Checked 2026-11-26.
  10. Rental power generators, Atlas Copco Rental. Rental company page: transformers up to 6,300 kVA and 25 kV. Checked 2026-11-26.
  11. T-030 Liquid-Cooled Generator Set Application Manual, Cummins. Section 2.4 (standby and prime rating definitions, 70% average load, 200 hours a year for standby) and Section 7.4, Table 53 (single- and three-phase formulas). Checked 2026-11-26.
  12. Basics of power system design (DG081001EN), Eaton. Three-phase kW and kVA formulas and worked example. Checked 2026-11-26.
  13. NFPA 110 Testing and Service Requirements for Standby Power Systems (webinar slides), Cummins, December 15, 2020. Wet stacking and low combustion temperature. Checked 2026-11-26.
  14. Tier 4 Final Technology Rentals, Cummins. Manufacturer page: SCR with diesel exhaust fluid on Tier 4 Final rental generators. Checked 2026-11-26.
  15. Final Rule for Control of Emissions of Air Pollution from Nonroad Diesel Engines and Fuel, US Environmental Protection Agency, June 29, 2004 (69 FR). Checked 2026-11-26.
  16. 40 CFR 1068.30, Definitions (nonroad engine), Electronic Code of Federal Regulations, current. Portable and transportable engines; 12-consecutive-month location rule, seasonal sources and replacement engines. Checked 2026-11-26.
  17. 40 CFR 60.4202, Emission standards for stationary emergency CI engines (manufacturers), Electronic Code of Federal Regulations, current. Paragraph (a)(2): Tier 2 or Tier 3 nonroad standards for 2007-and-later emergency engines of 37 kW and up, 2,237 kW or less, under 10 L per cylinder, other than fire pump engines. Checked 2026-11-26.
  18. 29 CFR 1926.405, Wiring methods, components, and equipment for general use, Occupational Safety and Health Administration. Paragraph (a)(2)(i), temporary wiring scope and removal. Checked 2026-11-26.
  19. 29 CFR 1926.404, Wiring design and protection, Occupational Safety and Health Administration. Paragraph (b)(1), GFCI or assured equipment grounding conductor program. Checked 2026-11-26.
  20. NFPA 1 excerpt, section 11.1.8 Temporary Installations (docket attachment), National Fire Protection Association, filed in OSHA docket OSHA-2006-0049. Older NFPA 1 text that refers to NFPA 70 Article 590; edition not identified in the excerpt. We could not access the current NFPA 70 text. Checked 2026-11-26.
  21. Why rent load banks for data center commissioning, Sunbelt Rentals. Rental company page: Level 4 and Level 5 commissioning tests. Checked 2026-11-26.