What a load bank test is and when you need one
You need a load bank test in two cases: a diesel set whose monthly exercise with building load doesn't reach 30% of nameplate kW or the manufacturer's exhaust temperature (the annual test), and a Level 1 system whose 36-month test needs extra load to reach its minimum.1 A load bank is a portable (or permanently installed) bank of resistors, sometimes with reactive elements, that turns the generator's output into heat; resistive/reactive units also simulate a lagging power factor. This guide covers standby generator testing under NFPA 110. For UPS and battery load tests, see UPS maintenance services. If you only need the equipment for data center commissioning, see load bank rental.
NFPA 110 (2016 edition) §8.4.2 says generator sets in service must be exercised at least monthly for at least 30 minutes, either at a load that keeps the manufacturer's minimum exhaust gas temperature or at not less than 30% of the standby nameplate kW rating.1 If a diesel set can't hit either target with building load, §8.4.2.3 adds the annual supplemental load test.1 That annual test and the longer 36-month test are the two jobs this page covers.
Gas (spark-ignited) generators are treated differently. The annual supplemental test in §8.4.2.3 is written for diesel-powered installations only.1 Gas sets still need the monthly exercise, and Level 1 gas systems still need the 36-month test, run at the available EPSS load (§8.4.9.5.3, 2016 edition).1
Resistive or resistive/reactive?
For routine NFPA 110 site testing, a resistive load bank is the common choice; Crestchic, a load bank manufacturer, calls resistive-only units the most common and cost-effective option for engine exercising and preventive maintenance.8 Even for site acceptance testing, Cummins says testing at 1.0 power factor is acceptable.1 Aggreko says lagging power factor testing with a resistive/reactive bank is needed for complete engine and alternator tests, which purely resistive banks can't provide.7 That matters more for commissioning and alternator troubleshooting than for the annual test.
Wet stacking and the load bank
Running a diesel generator lightly loaded can leave unburned fuel in the exhaust, and a load bank is one way to put real load on it. Cummins warns that "wet stacking" may deposit unburnt fuel into the exhaust system, and that low combustion temperature may increase soot and foul aftertreatment.1 Crestchic says a resistive load bank is ideal for clearing carbon build-up in the engine.8 For what long light-load running does to injectors, rings and liners, see wet stacking damage and repair.
If your monthly logs show a diesel set running well under 30% of nameplate and not reaching the manufacturer's minimum exhaust gas temperature, expect the annual test to be required, and tell the provider so they can inspect for wet stacking before loading the engine.
What NFPA 110 requires: monthly, annual and 36-month tests
NFPA 110 sets three recurring load tests, and only diesel sets that fail the monthly load target need the annual load bank test. The table pulls the wording from the 2016 edition, as quoted by Cummins in a December 2020 webinar, and the same §8.4.2.3 text as quoted in a federal CMS survey record (CMS applies the 2010 edition).13 Section numbers can move between editions, so check the one your AHJ enforces. We couldn't review the 2025 edition, so this page sticks to the text we could verify.
| Test | Section (edition) | Applies to | Minimum load | Minimum duration |
|---|---|---|---|---|
| Monthly exercise | §8.4.2 (2016) | Generator sets in service | ≥30% of standby nameplate kW, or load that keeps the manufacturer's minimum exhaust gas temperature | 30 minutes, at least once a month |
| Annual supplemental load test | §8.4.2.3 (2016; same text quoted by CMS) | Diesel installations that don't meet §8.4.2 | 50%, then 75% | 30 min at 50% + 60 min at 75% = 1.5 continuous hours |
| 36-month test | §8.4.9 (2016) | Level 1 emergency power supply systems (EPSS) | Diesel: ≥30% (load bank permitted) or manufacturer's exhaust temperature; spark-ignited: the available EPSS load (§8.4.9.5, 2016) | The system's assigned class duration; may stop after 4 continuous hours if the class is longer |
The 36-month test in detail
Level 1 systems must be tested at least once within every 36 months, continuously for the duration of their assigned class. Where the class is longer than 4 hours, NFPA 110 (2016 edition) §8.4.9.2 permits ending the test after 4 continuous hours.1 For diesel sets, §8.4.9.5 (2016) sets the minimum load as at least 30% of nameplate kW, with a supplemental load bank permitted to reach it, or a load that maintains the manufacturer's minimum exhaust gas temperature.1 The test is started by operating transfer switch test functions or by opening the normal-power supply to the transfer switches, and §8.4.9.4 (2016) says power to non-EPSS loads doesn't have to be interrupted.1
Combining the tests into one visit
You can run the 36-month test, one monthly test and one annual test as a single test under NFPA 110 (2016 edition) §8.4.9.6.1 When the 36-month and annual tests are combined, §8.4.9.7 (2016) says the first portion runs at no less than the 36-month minimum load, the last hour runs at no less than 75% of nameplate kW, and the total duration follows the class rules above.1 In a year when both are due, that usually means one longer site visit instead of two.
Plan the annual test: load steps for your generator
A load bank test plan sets which test is being run (annual, 36-month or combined), the load steps and durations, the readings and how often they're taken, who witnesses the test and what the report will contain; agree it with the provider before the visit. For the annual test, enter your generator's standby nameplate kW to see the load for each step and the smallest load bank that covers the test. The steps come from NFPA 110 (2016 edition) §8.4.2.3.1
NFPA 110 annual load bank test calculator
Calculator| Step | % of nameplate | Load | Duration |
|---|
Minimum test time
–
Load bank needed (at least)
–
Steps per NFPA 110 §8.4.2.3 (2016 edition; a CMS survey record quotes the same text, and CMS enforces the 2010 edition for hospitals). This test applies to diesel generator sets that don't meet the monthly exercise in §8.4.2 (at least 30% of nameplate kW, or the manufacturer's minimum exhaust gas temperature). Enter the standby nameplate kW. Confirm the edition your authority having jurisdiction (AHJ) enforces. The load bank should be rated for at least the highest step. Planning aid only, not engineering advice.
The load bank figure assumes the bank carries the whole 75% step by itself, so the test doesn't depend on what the building happens to draw that day. If you plan to count building load toward a step, agree that with the provider in advance and make sure the readings show the total load.
Hospitals: CMS enforces the 2010 edition, and the Joint Commission moved its rules
For Medicare and Medicaid certification, hospitals are held to the NFPA 110 2010 edition, because that's the edition CMS incorporates; state or local authorities may also enforce a newer edition. 42 CFR 482.15(e)(2) requires hospitals to implement the emergency power inspection, testing and maintenance requirements of NFPA 99, NFPA 110 and the Life Safety Code, and §482.15(h)(1)(xii) incorporates the 2010 edition of NFPA 110. NFPA 99 and NFPA 101 are incorporated as their 2012 editions.2
The CMS Life Safety Code survey tag for generators (K918), used for hospitals and other surveyed facilities, describes generators "exercised under load 30 minutes 12 times a year in 20-40 day intervals" and exercised once every 36 months for four continuous hours. NFPA 99 (2012 edition) §6.4.4.1.1.4(A) sets the same 20-to-40-day spacing.3 Twelve tests a year isn't enough on its own if the gap between two of them falls outside that window.
The Joint Commission requirement has moved. Before 2026, hospital generator testing sat in standard EC.02.05.07; the Joint Commission's own document review tool (effective March 1, 2024) lists EP 9 as a 4-hour load test once every 36 months and EP 10 as running that test at no less than 30% of nameplate.5 Joint Commission slides from August 2025 show a new Physical Environment (PE) chapter effective January 2026, with utility systems under PE.04.01.03, and mark the detailed EC inspection, testing and maintenance standards as deleted.4 Our reading is that the test frequencies now come mainly from the NFPA editions CMS enforces. Ask your accreditation contact which requirements your surveyors will cite.
How a load bank test is done, step by step
A typical service visit runs from pre-checks through stepped loading, recorded readings, a stepped cool-down and a written report. The sequence below reflects common provider practice; it isn't a standard, and the provider's plan for your unit governs.
- Confirm which test is due. Annual, 36-month or combined, based on your logs, the generator's class and the edition your AHJ enforces.
- Pre-test inspection. Coolant, oil and exhaust are checked before load is applied.9 Fuel level should cover the full run. NFPA 110 (2010 edition) §8.3.8 also calls for an annual fuel quality test using ASTM-approved methods.3
- Connect the load bank. The load bank is cabled to the generator output. How depends on your installation, so ask whether your set has a dedicated load bank connection or needs temporary cabling by a qualified electrician. Cummins recommends specifying a permanent load bank so weekly testing can be properly loaded.1
- Start, warm up and apply the steps. Apply the steps from your test plan (see the calculator above), without breaks between them.
- Record readings at set intervals. Ask for voltage, amperage, frequency, oil pressure, coolant temperature and exhaust temperature at each step.
- Step down and cool down. Step the load down gradually rather than dropping it all at once (Holt Industrial Rentals, for example, steps down in 25% increments), then let the engine run unloaded to cool before shutdown.9
- Restore and report. The set goes back to automatic standby, and the provider delivers a written report.
Will the building lose power? Ask the provider whether your annual test can run on the load bank alone while the building stays on utility power; that depends on how the set is connected. The 36-month test is different: it's started through the transfer switches, so emergency loads move to the generator, though NFPA 110 (2016 edition) §8.4.9.4 doesn't require interrupting non-EPSS loads.1 If you also want switchgear tested, ask whether an electrical testing provider can work in the same shutdown window.
What the load bank test report should contain
The report is your proof of compliance, so it should show the load, the time at each step and the readings, plus anything that went wrong. NFPA 110 (2016 edition) §8.5.1 requires records of all inspections, operational tests, exercising, repairs and modifications, and §8.5.2 says they must be available to the AHJ on request.1 Under §8.5.3 (2016), the permanent record must include:1
- the date of the maintenance report;
- identification of the servicing personnel;
- any unsatisfactory condition and the corrective action taken, including parts replaced;
- testing of any repair for the time recommended by the manufacturer.
Ask for these items as well. They aren't quoted from a standard; they're what makes a report easy to defend later:
- generator make, model, serial number, nameplate kW and hour meter reading;
- the load bank's ID and rating;
- the load applied at each step, with actual start and stop times;
- voltage, amperage, frequency, oil pressure, coolant temperature and exhaust temperature at a set interval;
- ambient temperature and who witnessed the test;
- a pass/fail statement and any recommended corrective actions;
- which NFPA 110 section and edition the test was run to.
How long the test takes and when to book
The load run itself is 1.5 hours for the annual test and up to 4 hours for the 36-month test; ask the provider for total on-site time, which adds connection, warm-up, cool-down and paperwork.1 The 36-month run is the system's class duration, so a system with a class under 4 hours has a shorter test.1
- Book ahead of the due date. Ask for a date before the anniversary of the last annual test, so a failed run or reschedule doesn't leave you out of compliance.
- Hospitals: protect the monthly spacing. NFPA 99 (2012 edition) §6.4.4.1.1.4(A) requires monthly tests between 20 and 40 days apart.3 If the load bank visit will count as a monthly test, place it so the gaps on both sides stay in that window.
- Combined tests need a longer window. Running the 36-month, annual and a monthly test together is permitted under §8.4.9.6 (2016), with the last hour at 75% under §8.4.9.7.1 Reserve the full class duration plus setup, and plan the shutdown window around it.
EPA run-hour limits for emergency engines
For compression-ignition (diesel) emergency engines covered by NSPS Subpart IIII, load bank testing counts against the hours allowed for maintenance and testing. 40 CFR 60.4211(f)(2) allows a maximum of 100 hours per calendar year for maintenance checks and readiness testing, and up to 50 hours of non-emergency operation under (f)(3) count toward that 100.6 The tests must be ones recommended by a government body, the manufacturer, the vendor, the grid operator or the insurer. More hours are allowed if your records show that federal, state or local standards require them.6
The NFPA 110 minimums use only a fraction of that: twelve 30-minute monthly runs (6 hours), a 1.5-hour annual test and, in the year it's due, a 4-hour 36-month test add up to about 11.5 hours, before warm-up and cool-down (less if you combine tests under §8.4.9.6, or if your system's class is under 4 hours).16 Spark-ignited (gas) engines fall under Subpart JJJJ, which we didn't check; confirm its limits with your air permit. Check your air permit and any state rules for diesel engines too.
What drives the cost of a load bank test
We haven't found credible published national pricing for load bank testing, so this page gives no dollar figures. Quotes usually turn on the same few factors:
- Generator size. Larger sets need a larger load bank, heavier cable and sometimes more than one unit.
- Test type and duration. A 1.5-hour annual test, a 4-hour 36-month test and a combined test take different amounts of technician time.
- Connection. A dedicated load bank connection is faster than temporary cabling, which may need an electrician.
- Access. Rooftop, basement or parking-garage generators can mean long cable runs or a crane or forklift for the load bank.
- Scheduling. Night or weekend windows, common in hospitals and data centers, can change labor rates.
- Bundled work. Pairing the test with annual maintenance, a fuel test or transfer switch testing can reduce repeat trip charges.
What a quote should itemize
Ask each provider to break the price into the same lines so you can compare them side by side:
- load bank size and type;
- cables and connection labor;
- technician hours;
- travel or trip charge;
- any after-hours premium;
- the written report;
- what happens, and what's billed, if the generator fails mid-test.
If you have qualified staff and only need the equipment, renting a load bank is the other route. You then take on the cabling, operation and the report yourself.
How to compare load bank testing providers
Compare providers on who runs the test, what equipment they bring and what the report looks like, not only price. Useful questions:
- Who does the work? Generator dealers, independent generator service firms and load bank rental companies all offer testing. Ask whether the technician is factory-trained on your engine brand or works for an authorized dealer.
- Technician certification. EGSA (the Electrical Generating Systems Association) offers Apprentice and Journeyman generator technician certifications and a separate load bank certification.1011 Ask which, if any, the assigned technician holds.
- Load bank rating and voltage. The bank should cover the highest step at your generator's voltage.
- Sample report. Ask for a redacted report from a recent job and check it against the list above.
- What happens on a failure. Will they stop the test, diagnose on site and quote repairs? Who decides whether to continue?
- Insurance and site rules. Tell them what your site requires before work starts, such as certificates of insurance, a safety plan or escorted access.
If the generator fails, the next calls are usually industrial generator repair and, for a long repair, a temporary generator to cover the outage risk. NFPA 110 (2016 edition) §8.5.3 expects the repair to be tested for the time the manufacturer recommends and recorded.1
Do load banks need to be calibrated?
The NFPA 110 text we reviewed doesn't set a calibration interval for load bank meters, so ask when the bank's metering was last calibrated, or have readings taken with separately calibrated instruments. Either way, the report should say which instruments the readings came from.
Limits of this guide
This page summarizes NFPA 110 as quoted from the 2016 edition, plus a CMS survey record that quotes the same annual-test text and some 2010-edition sections. We couldn't review the 2025 edition, and section numbers and wording may differ in it. Your AHJ, insurer or accreditor decides which edition applies. We haven't confirmed which Joint Commission PE-chapter requirements replace each former EC.02.05.07 element, or which non-hospital programs still use EC.02.05.07. The EPA figures cover only engines under 40 CFR Part 60 Subpart IIII; we didn't check Subpart JJJJ or state rules. Test procedures and report contents beyond the NFPA text reflect common provider practice, not a standard. This is general information, not engineering or legal advice.
What to send for an accurate quote
A provider can price the job quickly if you send the generator details, the test you need and how they'll reach the unit:
- Generator make, model and standby nameplate kW, plus voltage and phase (copy them from the nameplate).
- Fuel type: diesel or natural gas.
- Which test is due: annual, 36-month or combined, and the system's level and class if you know them.
- The load your recent monthly tests reached, as a percentage of nameplate kW or as exhaust temperature (have the logs ready; providers may ask for them).
- Whether there's a dedicated load bank connection, and where the generator sits (roof, ground, vault, garage).
- Where a load bank trailer can park and how far that is from the generator.
- Allowed work windows, site access rules and whether it's a CMS-surveyed or Joint Commission-accredited facility.
- The report format your AHJ, insurer or surveyor expects.
Providers may ask for nameplate photos or logs when they contact you. Put those details in the form and request quotes.
Get quotes through Critical Power Index
Send one request with your generator details and the test you need. We review it and look for up to three independent providers that serve your area and offer load bank testing. If we can't find a match, we'll tell you. Providers contact you directly, and you decide whether to hire anyone. It's free for facilities. Providers may pay us a referral fee (see the referral disclosure). Critical Power Index is a referral service, not an electrical contractor, and we don't perform or supervise testing. Here's how requests are handled.
Request load bank testing quotes
Sources
- NFPA 110 Testing and Service Requirements for Standby Power Systems (webinar slides quoting NFPA 110, 2016 edition), Cummins Inc., December 15, 2020. Source for NFPA 110 (2016) §§8.4.2, 8.4.2.3, 8.4.9 to 8.4.9.7 and 8.5, plus Cummins guidance on wet stacking, site acceptance testing power factor and permanent load banks. Checked 2026-11-26.
- 42 CFR 482.15, Condition of participation: Emergency preparedness, Electronic Code of Federal Regulations (eCFR). Paragraphs (e)(2) and (h)(1)(xii). Checked 2026-11-26.
- CMS survey record quoting NFPA 110 (2010) and NFPA 99 (2012), tag K918, Centers for Medicare & Medicaid Services, QCOR, Survey dated September 17, 2020. Federal survey record for an ambulatory surgery center; cited only for the K918 tag text and the standards text it quotes. Checked 2026-11-26.
- Updated Accreditation Manual: Physical Environment Chapter (accessible slides), The Joint Commission, August 15, 2025. Checked 2026-11-26.
- Hospital Life Safety & Environment of Care Document List and Review Tool, The Joint Commission, Effective March 1, 2024. Pre-2026 EC.02.05.07 EP 9 and EP 10. Checked 2026-11-26.
- 40 CFR 60.4211, What are my compliance requirements if I am an owner or operator of a stationary CI internal combustion engine?, Electronic Code of Federal Regulations (eCFR). Paragraphs (f)(2), (f)(2)(i) and (f)(3). Checked 2026-11-26.
- Resistive/reactive load banks, Aggreko. Vendor page. Checked 2026-11-26.
- Why use a load bank?, Crestchic Loadbanks. Vendor page (load bank manufacturer). Checked 2026-11-26.
- Load bank testing procedures for reliable generator operation, Holt Industrial Rentals, March 16, 2026. Vendor page; describes its own procedure. Checked 2026-11-26.
- Generator Technician Certification, Electrical Generating Systems Association (EGSA). Apprentice and Journeyman levels. Checked 2026-11-26.
- Load Bank Certification, Electrical Generating Systems Association (EGSA). Checked 2026-11-26.