When you need to rent a load bank
A load bank is a self-contained device that applies a controlled, measurable electrical load to a generator, UPS or battery system, so you can test the source at a known load.2 Sunbelt Rentals describes it as a way to draw power from utility or generator sources and "convert it into a measurable and controllable load."13 Most of that energy leaves the unit as heat.1 You rent one when you need that known load and the building can't supply it on demand.
The common reasons facilities rent one:
- Generator commissioning and site acceptance. Cummins lists verifying that a new generator set "can achieve full nameplate rating in one step" among its site testing expectations.6 A new building rarely has enough connected load to do that.
- NFPA 110 annual supplemental load test. Diesel generators that don't meet the monthly loading requirement need an annual test with supplemental load (details below).6
- Clearing wet stacking. Cummins warns that wet stacking "may deposit unburnt fuel into engine exhaust system."6 Crestchic says a resistive load bank is "ideal for clearing carbon build-up in the engine."4
- UPS, battery and DC system tests. Aggreko rents DC load banks to test "batteries and UPS across a range of voltages," and lists UPS, transformers and PDUs among the equipment its resistive/reactive units test.21
- Data center commissioning. Sunbelt says a commissioning load bank "allows you to perform Level 4 and Level 5 testing."13 Sunbelt Solomon, a power services company unrelated to Sunbelt Rentals, describes Level 5 integrated systems testing as the stage when "load banks simulate full operational conditions to prove that all systems work together."14
Need the test run and documented instead? See rent or hire below.
Resistive vs reactive vs resistive/reactive load banks
Pick resistive for engine and kW testing, and resistive/reactive when you need to test the engine and alternator together at the generator's rated power factor. Aggreko says resistive load banks apply "a purely resistive load, converting electrical energy into heat," while resistive/reactive units add "an inductive element, which simulates a lagging power factor."1 Aggreko adds that lagging power factor testing "is vital for complete engine and alternator tests," which resistive-only units can't provide because they test only at unity power factor.1
Most generator sets are specified at 0.8 power factor, says Avtron, a load bank manufacturer, so a 500 kVA set "would only be able to deliver 400kW into a purely resistive load." In that test the engine usually reaches full load, but the alternator sees only 80% of its rated current.3
That doesn't mean every test needs a reactive unit. For site testing, Cummins says "Testing at 1.0 PF is acceptable."6 Crestchic calls resistive-only "the most common and cost effective option."4 The usual pattern: resistive for routine and code tests, resistive/reactive when a specification, commissioning plan or manufacturer asks for rated-power-factor testing.
| Type | Load it applies | Typical rental use | Limits | Fleet examples |
|---|---|---|---|---|
| Resistive | Real power (kW) at unity power factor, dissipated as heat1 | Generator exercise, NFPA 110 annual tests6, wet-stacking burn-off4 | On a 0.8 PF generator, loads the alternator to only about 80% of rated current3 | United Rentals lists 100 to 3,000 kW units and 17 to 20 kW rack-mount units9 |
| Resistive/reactive (R/L, inductive) | kW plus inductive kVAR, typically 0.8 lagging power factor1 | Commissioning and full engine-and-alternator tests; transformers and PDUs1 | Not required for every site test6 | Aggreko: 240 kW to 6.25 MVA, 380 to 690 V1 |
| Capacitive | Leading kVAR | Aggreko: to counteract inductive load "or introduce capacitive loads to test specific equipment"2 | Specialty item; confirm your test plan calls for it | United Rentals lists a 2,000 kVAR unit at 480 V9 |
| DC | DC load | Batteries, UPS and DC power supplies221 | Doesn't test an AC generator | Herc, Sunbelt and Aggreko list DC rentals15122 |
| Liquid-cooled | Heat delivered to a liquid cooling system instead of the air | Data center liquid cooling tests216 | Only relevant where the cooling under test is liquid | Aggreko lists a 500 kW unit; EquipmentShare rents them for data centers216 |
For generators at distribution voltage, medium-voltage load banks connect directly; Crestchic lists units up to 33 kV.5
For indoor UPS or generator rooms, ask for compact units; Herc says some of its rentals "can fit through doorways."15
| Provider | Types listed | Sizes listed | Voltages listed |
|---|---|---|---|
| United Rentals9 | Resistive (networkable), resistive/reactive, capacitive, rack-mount | 17 to 20 kW rack-mount; resistive 100 to 3,000 kW; R/R 240 kW to 5,000 kW; capacitive 2,000 kVAR | 208, 240, 415, 480, 600 V |
| Aggreko12 | Resistive, resistive/reactive, capacitive, DC, liquid-cooled | R/R 240 kW to 6.25 MVA; resistive up to 5 MW in a single unit | R/R 380 to 690 V |
| Crestchic USA175 | Manufacturer and rental supplier (owned by Aggreko since 202320) | 100 kW to 7,000 kW | Medium-voltage units up to 33 kV |
| Herc Rentals15 | Resistive, DC, water-cooled, compact units | Units listed include 100, 125, 310 and 600 kW, plus a 500 kW water-cooled unit | 240 and 480 V on one listed unit; otherwise not stated on category page |
| Sunbelt Rentals12 | Resistive, reactive, DC | Not stated on category page | Not stated on category page |
Listed for size reference only. Critical Power Index has no partnership with these companies, and their fleets and availability change.
How to size a load bank to your generator or UPS
Size the load bank to at least the highest load step your test plan applies, minus any real building load you'll carry during the test (agree that with the provider in advance). Then match the voltage and connection. The test you're running sets the highest step; UPS and battery tests are sized differently (see below).
Commissioning and acceptance tests
Plan for 100% of the generator's nameplate kW. Cummins' site testing expectations include full nameplate rating in one step.6 For a 1,000 kW generator, that means at least 1,000 kW of load bank. If you need to reach that in a single step, confirm the rental unit (or linked group of units) can apply full load at once rather than only in increments.
NFPA 110 annual and 36-month tests
For an NFPA 110 annual load bank test, size the bank to at least 75% of the generator's nameplate kW, less any building load the generator carries during the test. The test steps to 50% for 30 minutes, then 75% for 1 continuous hour (section 8.4.2.3, same wording in the 2010 and 2016 editions).67 For a Level 1 diesel 36-month test, size to at least 30% of nameplate kW. If you combine it with the annual test, size to 75%, because the last hour must run at no less than 75% (8.4.9.5.1 and 8.4.9.7, 2016 edition).6 Section numbers can move between editions, so check the edition your AHJ enforces.
For the full test sequence, what the report should contain and the CMS rules for hospitals, see our NFPA 110 load bank testing guide. It includes a load-step calculator for your generator's kW.
Reactive units: size in kVA as well as kW
Rental fleets may list resistive/reactive units in kVA or kW. United Rentals' list mixes 1,800 kVA and 3,700 kVA units with 2,600 kW and 5,000 kW units.9 At 0.8 power factor, kVA equals kW divided by 0.8, so a 1,000 kW generator rated at 0.8 PF is a 1,250 kVA machine. Avtron's 500 kVA / 400 kW example uses the same ratio.3 Give the provider both figures from the nameplate.
Match the voltage, current and connection
Match the load bank's voltage to the generator or UPS output. United Rentals lists 208, 240, 415, 480 and 600 V units, and some of its resistive/reactive units cover 380 to 480 V.9 To estimate the current the cables will carry, Cummins gives the three-phase formula amps = kW × 1,000 ÷ (volts × PF × 1.732).11 A 1,000 kW load at 480 V and unity power factor works out to about 1,203 A; the same kW at 0.8 PF is about 1,504 A. Large tests can use several networked units. United Rentals lists networkable resistive units, and Aggreko says its modular design "enables load scaling."92
UPS and battery tests
For a UPS test, size the load bank to the UPS output kW rating, not its kVA. If the nameplate gives kVA and a rated power factor, kW is the kVA times that power factor. Match the UPS output voltage and phase: Aggreko says most load banks are designed for a specific nominal voltage, a higher voltage "can cause overheating and equipment damage," and a lower one reduces the available load.2
Battery discharge tests use a DC load bank. Herc lists DC load banks for testing UPS units, and Aggreko says its DC units can "discharge batteries at your desired voltage and current," listing DC load banks from 28 V to 700 V.1521 Give the provider the battery string's DC voltage and the discharge current your test procedure calls for. Follow the UPS or battery manufacturer's procedure for load steps and duration. If you'd rather have the battery work done for you, it's part of UPS maintenance and battery testing.
Cables, connection and an operator: what a rental includes
What comes with a load bank rental varies by provider, so ask before you compare prices. Some providers bundle more than the unit. Aggreko says it delivers to site and helps with setup, and offers "certified technicians to run step tests and configure equipment."2 Sunbelt Solomon (again, not part of Sunbelt Rentals) says its fleet includes "all necessary cabling."19 A bare rental may be just the unit on a trailer.
Settle these before delivery day:
- Cable. How many feet, what size, and how many sets per phase for your test current. Measure the distance from the load bank's parking spot to the generator's output breaker or connection cabinet.
- Connection point. Does the generator have a load bank breaker, a cam-lok docking cabinet, or do lugs need to be landed on the breaker? Who makes and breaks the connection, and are they qualified to do it on your equipment?
- Placement and heat. Resistive load banks turn the test energy into heat.1 Plan a spot outdoors or in a space where the exhaust air can't recirculate, away from intakes, people and anything heat-sensitive.
- Control and data. Ask whether the unit logs voltage, current, frequency and kW at each step, and whether you get the data file. If several units are networked, ask who runs the master controller.
- Fuel. Have enough fuel for the full test plus cool-down. United Rentals estimates a heavy-duty 200 kW generator "will likely consume up to 15 gallons per hour."10 Larger sets burn more.
- Operator. Decide whether the provider's technician runs the test or your own generator technician does.
How far ahead to book and how long you'll need it
Book as soon as your test date is set, and earlier for specialty units. We haven't found published lead times for load bank rentals. Some providers advertise fast turnaround: Herc tags some load banks on its category page "Same Day Rental," and Aggreko says its equipment "is available at short notice."152 Those are vendor claims, and availability depends on your location and dates. Confirm early for multi-megawatt, resistive/reactive, medium-voltage or liquid-cooled units, and for tests that need several networked units at once.
Code tests keep the unit under load for hours, not days. The NFPA 110 annual test is 1.5 continuous hours at load, and the 36-month test runs for the system's class duration, up to 4 continuous hours where the class is longer.6 Add time for delivery, setup, connection, cool-down and teardown. Commissioning programs and data center integrated tests can keep units on site for days or weeks, so ask for weekly and monthly rates as well as daily ones.
Rent a load bank or hire a load bank testing service?
Rent the load bank when you already have a qualified person to run the test and keep records. Hire a testing service when you need the whole job, including the written record a surveyor or inspector will ask for.
Rent the equipment
A good fit when your generator dealer, electrical contractor or commissioning agent has a test plan and the people to run it, or when a data center commissioning schedule needs units on site for days. You control the schedule; you also own the setup, the operation and the documentation.
Hire a testing service
A good fit for NFPA 110 annual and 36-month tests where you need the test run and documented. Hospitals that participate in Medicare answer to CMS, which enforces NFPA 110 (2010) through 42 CFR 482.15.8 A load bank testing provider brings the unit, cables and technician, and gives you the report. For surveyed sites, confirm the report will include the records your surveyor expects.
Buying, or installing a permanent load bank, is the third option. Renting fits annual, 36-month and one-off commissioning tests. When a generator needs added load for monthly or weekly exercise, Cummins recommends specifying "a permanent load bank to the system to allow for proper loading during weekly testing."6 Some load bank manufacturers don't rent direct. Asked whether it rents its units, Avtron answers "Directly no" and points to rental companies that stock them.18 Others, such as Crestchic, both make and rent load banks.17 If the test turns up a problem with the engine, alternator or controls, that becomes generator repair work, which may be a different provider.
What rental costs, and why rates aren't published
There's no credible national price list for load bank rental, so we don't publish one. United Rentals, Sunbelt, Herc and EquipmentShare all ask for a location before they show rates.9121516 Figures that circulate online tend to be single-market estimates with unnamed sources.
What moves the quote:
- Size and type. Kilowatt rating, and resistive vs resistive/reactive. Crestchic calls resistive-only the most cost-effective option.4
- Duration. Day, week or month. A 1.5-hour annual test and a two-week commissioning program are priced very differently.
- Delivery distance and access. Trailer units need a truck and a place to park; compact or rack-mount units may need a crew to move them indoors.
- Cables and accessories. Ask whether cable and connection hardware are included or billed separately.
- Technician time. Setup, operation and teardown hours, and whether the work falls outside normal hours.
- Specialty units. Liquid-cooled, DC, capacitive and medium-voltage units are a narrower market than standard air-cooled resistive banks.
Ask each provider to break those items out, so you can compare quotes line by line.
How to compare rental providers
Compare providers on fit for your test, not just day rate. Ask each one:
- Which exact unit will you send (type, kW or kVA, voltage, power factor), and can it apply full load in one step if my plan needs that?
- How many feet of cable come with it, at what size, and what connection hardware?
- Is a technician included? Ask what training or certification they hold, for example a generator technician certification or manufacturer training, and, for broader electrical acceptance testing, whether the firm is NETA accredited.
- Does the unit log readings at each step, and in what format do I get the data?
- When was the unit's metering last checked or calibrated?
- Who is responsible for setup, connection and teardown, and what insurance do you carry for work on my site?
- What happens if the unit faults during the test window: is a replacement available, and how far away is it?
Limits of this guide
This is general buyer guidance, not engineering advice or a test procedure. NFPA 110 text is quoted from the 2010 and 2016 editions as reproduced by CMS and Cummins. We could not review the 2025 edition, and section numbers may differ in it. Your AHJ, accrediting body, insurer or equipment manufacturer may require a different load, power factor, duration or record. Fleet sizes and voltages come from provider pages checked on November 26, 2026; inventory and availability change by location. We don't publish rental prices because no credible national source exists. Connecting a load bank to energized equipment is hazardous work for qualified people only.
What to send for an accurate quote
Most of this is on the generator or UPS nameplate and in your test plan. Send:
- Equipment under test: generator or UPS make and model, kW and kVA rating, rated power factor, voltage, phase and frequency. For a battery or DC test, the DC voltage and current.
- The test: commissioning, NFPA 110 annual, 36-month, wet-stacking burn-off or data center integrated test, with the load steps and durations if you have them.
- Type you think you need: resistive, resistive/reactive (and at what power factor), DC, capacitive or liquid-cooled. Say if a specification requires a particular power factor.
- Connection: load bank breaker, cam-lok cabinet or lugs, and the cable distance from parking spot to connection point.
- Site: ZIP code, indoor or outdoor placement, access limits (doorways, elevators, truck access), and noise or hours rules.
- Dates and duration: delivery and pickup dates, test window, and whether you need after-hours work.
- Labor: equipment only, or a technician to set up, run the test and write the report.
Put that in the form and request quotes from providers that serve your area. If you also need a temporary generator during the work, add it to the same request or see temporary power rental.
Get quotes through Critical Power Index
Send one request. A person at Critical Power Index reads it and looks for up to three independent providers that serve your ZIP code and offer load bank rental. We can't promise a match, a response or a response time. If we can't find a provider, we'll email you. Providers contact you directly, and you decide whether to hire anyone. It's free for facilities. Providers may pay us a referral fee (see the referral disclosure). We're a referral service, not a contractor, and we don't perform, supervise or check the work. We handle commercial, industrial, healthcare and data center sites; we don't place requests for home or portable generators or for load bank purchases. See how it works for the full process.
Sources
- Resistive reactive load bank rental, Aggreko. Checked 2026-11-26.
- Load bank rental, Aggreko. Checked 2026-11-26.
- Why Test a Diesel Generator with a Resistive Reactive Load Bank?, Avtron Power Solutions. Page last modified July 11, 2024. Manufacturer article. Checked 2026-11-26.
- Why use a load bank?, Crestchic Loadbanks. Manufacturer page. Redirects to loadbanks.com, a Crestchic domain. Checked 2026-11-26.
- Crestchic Loadbanks home page (medium-voltage load banks), Crestchic Loadbanks. Checked 2026-11-26.
- NFPA 110 Testing and Service Requirements for Standby Power Systems (webinar slides), Cummins Inc., December 15, 2020. Quotes NFPA 110 (2016 edition) sections 8.4.2, 8.4.2.3 and 8.4.9 through 8.4.9.7; includes Cummins site testing expectations and its permanent load bank recommendation. Checked 2026-11-26.
- Statement of Deficiencies, Life Safety Code tag K918 (survey of September 17, 2020), Centers for Medicare & Medicaid Services, QCOR, September 17, 2020. Federal survey record quoting NFPA 110 (2010 edition) section 8.4.2.3. Checked 2026-11-26.
- 42 CFR 482.15, Condition of participation: Emergency preparedness, eCFR, U.S. Government Publishing Office. Paragraph (h)(1)(xii) incorporates NFPA 110, 2010 edition. Checked 2026-11-26.
- Load banks for rent, United Rentals. Fleet list as shown on the check date; rates require a location. Checked 2026-11-26.
- Generators for rent, United Rentals. Checked 2026-11-26.
- T-030 Liquid-Cooled Generator Set Application Manual, Cummins Inc.. Section 7.4, Useful Formulas. Checked 2026-11-26.
- Load bank rentals, Sunbelt Rentals. Checked 2026-11-26.
- Why rent load banks for data center commissioning, Sunbelt Rentals. Checked 2026-11-26.
- Data Center Commissioning 101: Validating Critical Power Systems with Load Banks, Sunbelt Solomon. Sunbelt Solomon is a separate company from Sunbelt Rentals. Checked 2026-11-26.
- Load bank rentals, Herc Rentals. Checked 2026-11-26.
- Liquid-Cooled Load Bank Rentals for Data Centers, EquipmentShare. Checked 2026-11-26.
- About us, Crestchic USA. Checked 2026-11-26.
- Can I rent your load banks?, Avtron Power Solutions. Checked 2026-11-26.
- Service providers, Sunbelt Solomon. Sunbelt Solomon is a separate company from Sunbelt Rentals. Checked 2026-11-26.
- Aggreko completes the acquisitions of Resolute Industrial and Crestchic plc, TDR Capital, February 23, 2023. TDR Capital is an Aggreko owner. Checked 2026-11-26.
- DC load banks and DC resistive load banks, Aggreko. Checked 2026-11-26.