Electrical testing services: tests, standards and how to get quotes

Electrical testing services are field tests of switchgear, breakers, protective relays, transformers and cables. They're done before new equipment is energized (acceptance testing, often specified to ANSI/NETA ATS) or on a schedule for equipment already in service (maintenance testing to ANSI/NETA MTS, at intervals set by NFPA 70B). Many of these tests need the equipment shut down, so scope and price depend on your equipment list and outage windows. Critical Power Index is a referral service, not a testing company: send one request and we share it with up to three providers that serve your ZIP code.

Updated · How we research

What an electrical testing company does

An electrical testing company brings calibrated test sets to your site, tests each piece of power equipment against a written standard, and gives you a report with readings, pass/fail results and recommended repairs. The point is to confirm that distribution equipment is installed correctly, still in good condition, and will operate when it has to.

The work splits into two jobs. Acceptance testing proves that new or modified equipment is ready to be energized. Maintenance testing checks whether equipment that's already in service is fit to stay in service. NETA publishes a separate American National Standard for each, ATS and MTS.12

This page is about field testing of building and plant power systems. If you need a product certified for sale (a lab safety listing) or rubber gloves and hot sticks dielectric-tested, those are different services handled by product labs and PPE test labs.

Testing often sits inside a larger job. These guides cover the most common ones:

Arc flash study

Maintenance condition affects how fast breakers clear a fault, so testing and the arc flash study and label update are often scoped together.

Switchgear maintenance

Cleaning, torque checks, breaker and relay testing on one lineup. See the switchgear maintenance guide.

Generator load testing

Standby generators are proven under load with a portable load bank. See load bank testing for NFPA 110.

UPS systems

NFPA 70B sets shorter intervals for UPS units than for most distribution gear (see the interval table below). See UPS maintenance and battery service.

Transformers

Dissolved gas analysis, turns ratio and insulation tests are read together to judge whether a unit can be repaired in the field, sent to a shop, rewound or replaced. See transformer diagnostic tests and repair options.

Acceptance testing (ATS-2025) vs maintenance testing (MTS-2023)

Use ATS for equipment that has never carried load in its current installation, and MTS for equipment that has. NETA says ATS is for "assessing the suitability for initial energization" and is meant to confirm that equipment is operational, within applicable standards and manufacturer tolerances, and installed per the design specifications.1 MTS, approved as an American National Standard on March 6, 2023, is meant to assess "suitability for continued service, condition of maintenance, and reliability."2

ANSI/NETA acceptance and maintenance testing standards compared (editions current as of November 2026, per NETA)
ItemAcceptance testingMaintenance testing
StandardANSI/NETA ATS, Standard for Acceptance Testing Specifications for Electrical Power Equipment and Systems1ANSI/NETA MTS, Maintenance Testing Specifications2
Current edition202532023 (superseded MTS-2019)2
Next revision planned2029320273
When it's usedNew equipment and systems, before initial energization1Equipment already in service, to judge whether it's fit for continued service2
Question it answersWas it built and installed right?Is it still safe and reliable enough to keep running?
Notable contentNew in 2025: Section 7.28 battery energy storage systems, Section 7.29 solar PV and Table 100.6 medium-voltage cable acceptance test values1Appendix B (frequency of maintenance tests) is included in MTS-20237

Specifications and contracts often name an edition. If yours cites an older ATS or MTS, the provider should test to that edition unless you agree otherwise in writing.

Which testing scope fits your situation

Start from what the equipment is doing now. This table maps common situations to the scope to ask for.

Matching a facility's situation to a testing scope, based on ANSI/NETA ATS, MTS and ECS and on NFPA 70B (2023 edition) as summarized by Eaton and e-Hazard
Your situationScope to request
New equipment, not yet energizedAcceptance testing to ANSI/NETA ATS1
Equipment in service, maintained to planMaintenance testing to ANSI/NETA MTS, at the NFPA 70B interval for its condition rating211
The last two maintenance cycles were missed, or both found problems needing major repairTreat as Condition 3: electrical testing at intervals of no more than 12 months for most distribution equipment1311
New build with a commissioning agentAcceptance testing of components, plus functional and integrated systems testing support if the job follows ANSI/NETA ECS316
A known problem, such as a breaker tripping under normal loadOffline enhanced tests, which NFPA 70B describes as useful when there's a problem with the equipment11

Where commissioning fits

Commissioning is bigger than acceptance testing. Acceptance testing checks each component; commissioning also checks that the whole system works the way the owner and designer intended. Writing in ACHR News in 2020, Chris Dansa, PE, of Vertiv's Electrical Reliability Services (a testing and commissioning provider) and co-author Leif Hoegberg described acceptance testing and equipment startup as "only two subsets of the electrical commissioning process," followed by functional performance testing (FPT) and integrated systems testing (IST).16

NETA publishes a separate commissioning standard, ANSI/NETA ECS (Electrical Commissioning Specifications). The current edition is 2024, with a new revision planned for 2028.3 On a data center, hospital or other new build with a commissioning agent, ask whether your testing firm is quoting component acceptance testing only, or also FPT and IST support. Generator and UPS commissioning can include load bank testing.

Common tests and what each one finds

Most testing jobs combine a handful of standard tests, chosen by equipment type. The table lists the ones you'll see most often in quotes and reports.

Common field electrical tests, what each is used to find, and the equipment usually tested (sources cited per row where available)
TestWhat it's used to findUsually applied to
Infrared thermographyHot connections and overheating parts while equipment carries load. NFPA 70B (2023) sets infrared scans for all equipment every 12 months in Conditions 1 and 2 and every 6 months in Condition 3.11All energized distribution equipment11
Insulation resistanceInsulation condition; listed among NFPA 70B's circuit breaker electrical tests11Switchgear, breakers, cables, transformers, motors
Contact resistanceResistance across contacts and jointsBreakers, switches, bus connections
Circuit breaker trip and timing testsBreakers that trip late, early or not at all; inverse-time and instantaneous trip testing are listed in NFPA 70B's breaker test table11Low- and medium-voltage power breakers, insulated- and molded-case breakers
Protective relay testingPickup and timing checks, and verification that settings match the coordination study11Electromechanical, solid-state and microprocessor relays11
Insulating fluid analysis, including dissolved gas analysis (DGA)Developing faults inside oil-filled transformers; IEEE C57.104-2019 is the guide for interpreting DGA results15Liquid-filled power and distribution transformers
Cable testingInsulation problems in new or aging cable; ATS-2025 added medium-voltage cable acceptance test values (Table 100.6)1Medium-voltage feeders and terminations
Power quality and metering verificationHarmonics, voltage problems and meters that read wrongService entrance, critical loads, revenue and submeters

Which tests need an outage

Some tests run with equipment energized and some don't. NFPA 70B (2023) sorts field tests into four categories: online standard (equipment connected to its supply), online enhanced, offline standard (disconnected from the supply or fed from an external test source) and offline enhanced (extra diagnostics used when there's a problem or a special application).11 Infrared scans are taken while equipment carries load. Insulation resistance, contact resistance and breaker trip tests are normally done offline. Ask each provider to split their scope into online and offline work so you can plan the shutdown.

How often equipment must be tested under NFPA 70B

NFPA 70B sets maximum test intervals of 12, 36 or 60 months for most distribution equipment, based on each item's condition rating. With the 2023 edition it changed from a "Recommended Practice" to a "Standard," which NFPA says gives "more enforceability for what must be done."10 The current edition is 2026, issued November 19, 2025 and effective December 9, 2025.8 A standard isn't automatically law, though. Reliable Media notes it becomes enforceable through adoption by a jurisdiction, a regulation, a contract or an insurer.14

Each item's condition rating comes from its physical condition, criticality and operating environment, and the highest of the three governs.11 See how NFPA 70B sets equipment condition.

Under the 2023 edition's table, electrical testing for most distribution equipment is due at intervals of no more than 60 months in Condition 1, 36 months in Condition 2 and 12 months in Condition 3.11 Relays and UPS units are on shorter cycles.

NFPA 70B (2023 edition) Table 9.2.2 maximum maintenance intervals, in months, for selected equipment and tasks, as reproduced by Eaton (March 2023)
EquipmentTaskCondition 1Condition 2Condition 3
All equipmentInfrared thermography12126
Switchgear, panelboards, breakers and relaysElectrical testing603612
Power and distribution transformersVisual inspection12126
Power and distribution transformersElectrical testing603612
Power cablesElectrical testing603612
Uninterruptible power suppliesVisual inspection631
Uninterruptible power suppliesElectrical testing1263

Source: Eaton, Understanding 2023 NFPA 70B (WP027024EN, March 2023).11 Eaton notes these intervals don't override the manufacturer's instructions. Electromechanical relays are tested at 36, 24 and 12 months. See switchgear and breaker intervals by condition for task-by-task and device-by-device rows.

The 2026 edition adds the P–F curve method for setting intervals and recognizes continuous thermal monitoring as an alternative to periodic infrared scans.912 We have not read its final Table 9.2.2, so confirm current values before you set a schedule.

NETA's Appendix B to MTS-2023 offers a second view of test frequency. NETA says "the ideal maintenance program is reliability-based, unique to each plant and to each piece of equipment."7

Who does the testing: NETA accreditation and technician levels

The main independent credential in this field is the NETA Accredited Company. NETA describes these as "third-party, independent firms involved in full-service testing, analysis, and maintenance of electrical power systems," and requires that they "be divested of competing service or manufacturing interests."4 Because of that rule, the field service groups of major switchgear manufacturers generally don't hold NETA accreditation. When we searched NETA's directory on November 26, 2026, Eaton, Schneider Electric, Siemens and ABB weren't listed.17 Eaton, itself a manufacturer, says manufacturers are qualified to test their own equipment,11 so an OEM can still be a reasonable choice, especially for warranty work or proprietary gear.

NETA also certifies individual technicians under the ANSI/NETA ETT standard. Certified technicians are employed by a NETA Accredited Company and hold certification at Level 2, 3 or 4. Level 1 trainees are not fully certified and must be supervised by a Level 3 or Level 4 technician.5

NETA technician certification levels: minimum related experience, cumulative training hours and role (NETA, checked November 2026)
LevelMinimum experienceSafety trainingElectrical trainingRole
Level 1, Trainee (not a NETA certification)None statedNot specifiedNot specifiedMust be supervised by a Level 3 or Level 4
Level 2, Certified Assistant Technician2 years40 hours160 hoursLimited testing, generally under direct supervision
Level 3, Certified Technician5 years64 hours400 hoursSupervises Levels 1 and 2; qualified to perform power switching
Level 4, Certified Senior Technician10 years104 hours600 hoursSupervises large projects and multiple crews; works independently

Source: NETA technician certification page.5 Level 1 is a trainee stage, not a NETA certification. It requires a high school diploma or GED, and its exam is given by the employer. Two or more years of technical education in an electrical field can count as up to one year of experience.

Certifications must be renewed. NETA's FAQ says Level 2 technicians need 24 continuing technical development credits every three years, and Levels 3 and 4 need 48.6 You can check a company's status in NETA's accredited company lookup. For arc flash work, our unranked list of NETA-accredited firms that perform arc flash studies shows which firms appeared in NETA's directory when we searched on November 26, 2026.

How to compare electrical testing providers

Compare quotes on scope first and price second. Two quotes for "testing the switchgear" can cover very different work. Ask each provider:

  1. Which standard and edition? ATS-2025, MTS-2023, ECS-2024 or your own specification, and which sections.
  2. Which tests on which equipment? A line-item list by device.
  3. Who will be on site? The NETA certification level of the lead technician, and whether a Level 3 or 4 will do any switching.
  4. Is the company NETA accredited, an OEM service group, or neither? Check accreditation yourself in the NETA lookup.
  5. What's in the report? Raw readings, pass/fail against which criteria, a deficiency list ranked by urgency, and the condition-of-maintenance decals NFPA 70B calls for11 if you need them.
  6. What happens when something fails? Whether minor corrective work (tightening, cleaning, resetting) is included, and how repairs are quoted.
  7. How are oil samples handled? Which lab runs DGA and fluid tests, and whether results are interpreted to IEEE C57.104. If results point to a developing fault, see what happens next with a failing transformer.

What drives the price of electrical testing

Price depends mainly on how many devices are tested, which standard applies (ATS, MTS or ECS) and how much outage time you can give. We found no reliable published price range for field testing, so we don't print one. These are the factors that change a quote:

  • Which standard applies. Acceptance testing to ATS, maintenance testing to MTS and full commissioning to ECS are different scopes.123 Commissioning with functional and integrated systems testing adds work beyond component tests.16
  • Equipment count and type. NFPA 70B sets separate tasks and intervals for each equipment type, from breakers and relays to transformers and cables.11 A complete equipment list helps providers price accurately.
  • Breaker sizes and trip units. Eaton's summary of NFPA 70B (2023 edition) notes that trip-function testing is optional for circuit breakers rated 250 A or less, and that breakers with electronic trip units only need calibration of all trip-unit functions verified with the manufacturer's specified test set.11 That can affect the scope of a quote for a panel full of small breakers.
  • Outages. Offline tests require the equipment to be disconnected from its supply.11 If you can only shut down at night or on weekends, say so up front.
  • Equipment condition. Condition 3 equipment is due as often as every 12 months rather than every 60, so the yearly cost of a program depends on how well the gear has been kept.1113
  • Lab work and studies. Ask whether oil sampling and DGA lab fees are included. NFPA 70B (2023) also calls for short-circuit, coordination and incident energy studies at intervals not exceeding five years,11 and a study update may be scoped alongside the testing.
  • Repairs found during testing. These are usually quoted separately. NFPA 70B (2026) now asks for a timeline to complete needed repairs.9

How long testing takes and when to book

Time on site depends on how many devices are tested and how long each outage window is, so ask each provider for a day-by-day plan and a report delivery date in the quote. Book ahead of any planned shutdown, because offline tests can only run while equipment is disconnected from its supply.11 If equipment has already failed, choose "Urgent: equipment is down now" in the form. We pass urgent requests on as soon as we've reviewed them, but providers set their own availability and we don't dispatch crews. For a fire, shock injury or other life-safety emergency, call 911.

Limits of this guide

This is general information, not engineering advice or a test specification. Intervals shown are from the 2023 edition of NFPA 70B as reproduced by Eaton; we have not read the final 2026 table, and your authority having jurisdiction, insurer or contract may require a different edition. Manufacturer instructions, your equipment's condition rating and your facility's risk assessment can all change what's required. Test scopes in the table are typical, not complete. Budget from written quotes.

What to send for an accurate quote

A provider can quote fastest when they know exactly what's on site and when they can reach it. Include as much of this as you have:

  • Job type: new installation (acceptance), periodic maintenance, commissioning support, or a specific problem.
  • Equipment list: switchgear lineups, switchboards, breakers by type and frame size, relays, transformers (kVA, voltage, liquid or dry), MV cable runs, ATS and UPS units.
  • One-line diagram and service voltage, if you have them.
  • Nameplate photos of the main gear.
  • The last test report and any open deficiencies.
  • Specification or contract language that names ATS, MTS, ECS or NFPA 70B, with editions.
  • Outage windows and access limits (night work, badging, escorts, confined spaces).
  • Site ZIP code and timeline.

Send what you have and request quotes. You can add details later when providers contact you.

Get quotes through Critical Power Index

Send one request and we'll review it, then share it with up to three providers that serve your ZIP code and list electrical testing among their services. They contact you directly to confirm scope and quote. It's free for facilities. Providers may pay us a referral fee, as explained in our referral disclosure. Critical Power Index isn't a contractor or testing company and doesn't perform or supervise any work. We don't verify NETA accreditation, so check it in NETA's lookup. You can read how requests are handled before you send yours.

Request electrical testing quotes

Sources

  1. ANSI/NETA ATS-2025 Standard for Acceptance Testing Specifications for Electrical Power Equipment and Systems, InterNational Electrical Testing Association (NETA). Checked 2026-11-26.
  2. ANSI/NETA MTS-2023 Standard for Maintenance Testing Specifications, NETA. Checked 2026-11-26.
  3. Standards Development (edition and revision schedule for MTS, ECS, ATS, ETT), NETA. Checked 2026-11-26.
  4. NETA Accreditation Overview, NETA. Checked 2026-11-26.
  5. NETA Technician Certification, NETA. Checked 2026-11-26.
  6. Contact Us and FAQs (recertification credits), NETA. Checked 2026-11-26.
  7. Frequency of Maintenance Tests, Appendix B of ANSI/NETA MTS-2023, NETA. Checked 2026-11-26.
  8. NFPA 70B: Standard for Electrical Equipment Maintenance (development page, current edition), National Fire Protection Association. Checked 2026-11-26.
  9. NFPA 70B, Standard for Electrical Equipment Maintenance, 2026 edition (product page), National Fire Protection Association. Checked 2026-11-26.
  10. NFPA 70B is a critical tool for reliability and safety, NFPA (Corey Hannahs), March 8, 2023. Checked 2026-11-26.
  11. Understanding 2023 NFPA 70B: Standard for electrical equipment maintenance (WP027024EN), Eaton (Scott Brady, PE), March 2023. Manufacturer white paper; source for the Table 9.2.2 values reproduced here. Checked 2026-11-26.
  12. Top NFPA 70B 2026 updates, Eaton. Checked 2026-11-26.
  13. The critical role of equipment condition assessments in NFPA 70B, e-Hazard. Checked 2026-11-26.
  14. NFPA 70B compliance guide, Reliable Media, July 2026. Checked 2026-11-26.
  15. IEEE C57.104-2019, Guide for the Interpretation of Gases Generated in Mineral Oil-Immersed Transformers, IEEE Standards Association, 2019. Checked 2026-11-26.
  16. Electrical commissioning and acceptance testing: are they one in the same?, ACHR News (Chris Dansa, PE, and Leif Hoegberg), November 4, 2020. Originally published in Mission Critical. Chris Dansa is with Vertiv's Electrical Reliability Services, a testing and commissioning provider. Checked 2026-11-26.
  17. Find a NETA Accredited Company (directory lookup), NETA. Searched by company name on November 26, 2026. Checked 2026-11-26.