Testing & studies · NFPA 70E

Arc flash study: when you need one, what it includes and how to get quotes

An arc flash study is an engineering analysis that calculates how much heat an arcing fault could release at each switchboard, panelboard and motor control center. If workers examine, adjust or service energized equipment and you don't have current incident energy data for it, you most likely need one: OSHA requires you to assess arc hazards, NFPA 70E requires labels, and a study is the usual way to produce both. The study turns its results into arc flash boundaries, PPE requirements and labels. It combines a short-circuit study, a protective device coordination study and an incident energy analysis, normally calculated with IEEE 1584-2018, and NFPA 70E requires the label data to be reviewed at least every five years.

We're a referral service, not an engineering firm. Tell us your ZIP code, roughly how much equipment is in scope and whether you have a current one-line diagram, and we'll look for up to three independent providers that serve your area and share your request with them.

Updated · How we research

What an arc flash study includes

An arc flash study is three linked calculations run on a computer model of your power system, plus the field work to build the model and the labels that come out of it. IEEE 1584.1-2022 sets out the minimum recommended scope of work and deliverables an owner can specify for this kind of study10, and the arc flash calculations are normally completed together with short-circuit calculations and protective device coordination21.

Short-circuit study

How much fault current is available at each bus, and whether breakers, fuses and gear are rated to interrupt or withstand it (the equipment duty check)18.

Coordination study

How fast each breaker, fuse or relay clears a fault, and whether the device nearest the fault trips first18.

Incident energy analysis

IEEE 1584-2018 calculations of the heat a worker could receive at a set working distance, in cal/cm², and the arc flash boundary at each location9.

Arc flash study, risk assessment or hazard analysis?

Providers use these terms loosely, so read the scope rather than the title. NFPA 70E requires an electrical safety program to include an arc flash risk assessment procedure5. OSHA notes that the incident heat energy estimate required for utility-type work is "often referred to as an arc flash risk assessment"6. In practice, the study is the engineering that produces the incident energy numbers your risk assessment, labels and PPE choices depend on.

Why the incident energy number matters

OSHA's fact sheet says arc temperatures can exceed 35,000 °F and that most arc flash burns happen when the arc ignites flammable clothing, not from the arc itself6. NFPA 70E defines the arc flash boundary as the distance where incident energy equals 1.2 cal/cm², roughly where an unprotected worker could get a second-degree burn6. The calculated value at each location tells workers how much arc-rated protection they need there.

Is an arc flash study required? OSHA, NFPA 70E and the NEC

No OSHA rule requires a document called an "arc flash study." But OSHA requires you to assess arc hazards and provide suitable PPE, NFPA 70E requires a risk assessment and labels, and a study is the usual way to produce that information.

Where arc flash requirements come from (US), as of November 26, 2026. Sources: OSHA, NFPA and Daily Reporter (numbered below). Check the editions your authority having jurisdiction (AHJ) enforces.
DocumentCurrent editionWhat it says about arc flashHow it becomes binding
OSHA 29 CFR 1910In forceAssess workplace hazards, including electric arcs; provide appropriate protective equipment. Utility-type work: estimate incident heat energy.678Federal regulation (or a state plan)
NFPA 70E2027 (effective May 6, 2026)Risk assessment procedure; equipment labels; label data reviewed at intervals not exceeding 5 years14Consensus standard. OSHA follows it but hasn't incorporated it by reference
NEC (NFPA 70) Section 110.162026Arc flash hazard marking on equipment13Adopted state by state
NFPA 70B2026Maintenance program; committee draft text calls for the study to be reviewed at least every 5 years (final wording unconfirmed)2425Adoption, insurer or contract

OSHA

OSHA's own guidance answers the most common question directly: "Existing regulations require that employers assess the workplace for hazards, including from electric arcs, but do not specify the components of the assessment."6 Employees exposed to electrical hazards must be provided with, and use, protective equipment appropriate for the body parts to be protected8. In the same fact sheet, OSHA says an arc flash study is "highly recommended for all employers whose workers may be exposed to electrical hazards, not just utility workers"6. The fact sheet is guidance and creates no new legal obligations6.

The rules are stricter for utility-type work. Under 29 CFR 1910.269(l)(8), the employer must assess the workplace for flame and arc hazards, make a reasonable estimate of incident heat energy, and provide arc-rated protection where that estimate exceeds 2.0 cal/cm²7. You don't have to be a utility for this to apply: OSHA says a worker who distributes electricity throughout a workplace, rather than just using it, is covered6.

OSHA's standards follow NFPA 70E, but OSHA "has never incorporated that consensus standard by reference"6. Separately, the General Duty Clause requires a workplace free from recognized hazards likely to cause death or serious harm6.

NFPA 70E

NFPA 70E is the standard most arc flash programs are built on, and NFPA describes it as helping employers comply with OSHA 1910 Subpart S and 1926 Subpart K1. The 2027 edition is current; it was issued April 16, 2026 and took effect May 6, 20261. The labeling text in its 2027 revision cycle requires a label to be updated when a review of the data finds a change that makes it inaccurate4, and Herzig Engineering, an engineering firm that sells arc flash studies, reports that the five-year review is unchanged in the published 2027 edition3. The 2027 edition also adds battery risk assessment requirements (new Article 360)2; if you have large UPS or battery systems, ask whether the study scope covers them, and see our guide to UPS maintenance and battery testing.

Is there an alternative to a full study?

Yes, within limits. NFPA 70E lets employers select arc flash PPE by either an incident energy analysis or the arc flash PPE category method4. The category method uses tables that list maximum available fault current, fault-clearing times and minimum working distances by equipment type, and an incident energy analysis is required where a system falls outside those limits28. Herzig Engineering reports that the PPE categories carried forward into the 2027 edition, with the tables' clearing times clarified as applying within the instantaneous trip region3. To use the tables, you still need the available fault current and clearing time at each location, so some short-circuit and coordination work is involved, and the label then shows a PPE category instead of an incident energy value4.

The NEC (NFPA 70)

Arc flash warning labels first appeared in the 2002 NEC, Section 110.16, according to a November 2026 summary in the Daily Reporter13. That summary says the 2026 NEC lists four items for the marking: nominal system voltage, arc flash boundary, available incident energy or minimum required PPE, and the date the assessment was completed13. Sources disagree on whether the 2026 edition removed the earlier 1,000-ampere threshold for service equipment, so confirm against the code text your state has adopted. NEC adoption is set by each state or local jurisdiction.

NFPA 70B

NFPA 70B, the electrical equipment maintenance standard, is in its 2026 edition24. Draft text from its revision cycle (we haven't confirmed the final 2026 wording) says the analysis "shall be reviewed for accuracy at intervals not to exceed 5 years" and that the most recent study be made available to the facility's electrical maintenance program coordinator25. Keeping the protective devices in the model working as designed is the job of switchgear and breaker maintenance.

Limits of this guide

This page summarizes standards, OSHA guidance and providers' published information. It isn't engineering or legal advice. Your AHJ, insurer or contract may enforce an older NFPA 70E or NEC edition, and we haven't confirmed which states have adopted the 2026 NEC. We cite NFPA 70E-2027 at the section level because we couldn't confirm every subsection number in the new edition, and our description of the PPE category table limits comes from 2024-edition committee text. IEEE 1584-2018 doesn't cover single-phase ac, dc or systems above 15 kV, so battery, dc and higher-voltage equipment need other methods. Timelines and prices come from provider firms' own pages and may not match your site.

When you need a new study or an update

A study is the usual way to get the incident energy data NFPA 70E labels and PPE choices rely on, so if workers examine, adjust or service energized equipment and you don't have current data for it, start there. After that, plan an update at least every five years and whenever the system changes enough to make the labels wrong.

  • No study, or labels without a traceable study. NFPA 70E makes the equipment owner responsible for documenting, installing and maintaining the label4.
  • The five-year review is due. NFPA 70E requires the data to be reviewed at intervals not exceeding 5 years4.
  • A major modification. OSHA says employers should calculate incident energy after each major modification of the electrical system or equipment6. A new service or transformer, a generator, a utility source change, replaced breakers or changed relay settings can all change fault current or clearing time.
  • Protective devices haven't been maintained. OSHA warns that if equipment isn't properly maintained, the calculated incident energy may not be accurate, because a slow breaker lets more energy through6. Testing breakers and relays is covered in our guide to electrical testing services.

If the original firm's model file is available, an update usually means checking what changed in the field and re-running the model. If it isn't, the provider may have to rebuild the model from field data. Ask for both prices when you request quotes.

How the study works, step by step

Most studies follow the same sequence: collect data, build and check a model, run the three calculations, then deliver labels and a report. One firm says most of its projects include two on-site visits15, and Zech Engineering says extra visits are common when critical data can't be captured on the first trip16.

  1. Define the scope. Agree on which buildings, voltages and equipment are included, which operating scenarios are modeled (for example, utility versus generator source)26, and what the deliverables are. IEEE 1584.1-2022 is written to help owners specify exactly this10.
  2. Get utility fault data. The available fault current at your service comes from the utility, and the provider may help you submit the utility's request forms15.
  3. Collect field data. Engineers or technicians verify the one-line diagram and record transformer ratings and impedances, conductor sizes and lengths, and protective device details1516.
  4. Build the model. The data goes into power system software. Firms we checked name SKM and EasyPower1516.
  5. Run short-circuit and duty checks. Fault current at each bus is compared with equipment ratings18.
  6. Run the coordination study. Device settings are checked so the right device trips first and clearing times are known21.
  7. Calculate incident energy. IEEE 1584-2018 equations give incident energy and the arc flash boundary at each location9.
  8. Review and recommend. The engineer flags overdutied equipment, poor coordination and high-energy locations, with mitigation options1626.
  9. Labels and final report. Labels, the report and a quality review make up the final phase16. Some firms produce labels only after you approve a preliminary report, then walk you through the findings15.

What IEEE 1584-2018 does and doesn't cover

If your last study used the 2002 method, label values may change when it's redone: the 2018 edition added three new electrode configurations, including horizontal conductors in a box, which produces the highest incident energy1112. IEEE 1584-2018 is still the active edition, and a revision project (P1584) is open9. It covers three-phase ac systems from 208 V to 15 kV. Single-phase ac and dc are outside its scope, and it doesn't make PPE recommendations9.

What goes on an arc flash label

NFPA 70E requires labels on switchboards, panelboards, industrial control panels, meter socket enclosures and motor control centers in other than dwelling units that are likely to require examination, adjustment, servicing or maintenance while energized4. Each label must show the nominal system voltage, the arc flash boundary, and at least one way of expressing the hazard: incident energy with the working distance or the PPE category (not both), the minimum arc rating of clothing, or a site-specific level of PPE4.

Hazard warning header
Wording, colors and format come from your label specification
1

Nominal system voltage

For example, the service or bus voltage at this equipment.

Required by NFPA 70E

2

Arc flash boundary

The distance at which incident energy falls to 1.2 cal/cm².

Required by NFPA 70E

3

At least one of these

(a) available incident energy and the working distance, or the arc flash PPE category, but not both; (b) minimum arc rating of clothing; (c) site-specific level of PPE.

Required by NFPA 70E

4

Date the assessment was completed

Listed in the 2026 NEC version of Section 110.16, as summarized by a trade publication. Applies where your state has adopted that edition.

Check your adopted NEC

+

Your own additions

Equipment name, study reference or other fields your specification asks for.

Optional

Illustration of the information NFPA 70E-2027 Section 130.5 lists for equipment arc flash labels, plus the 2026 NEC date item. Not a label template and not drawn to any label standard. Sources: NFPA committee text4; arc flash boundary definition as quoted by OSHA6; 2026 NEC item per Daily Reporter13.

The label must be durable enough for its environment, and the equipment owner is responsible for it4. In supervised industrial installations where only qualified persons monitor and service the system, the information may be documented instead of labeled4.

What a complete study should deliver

A complete study gives you a validated one-line diagram, the three sets of calculations, labels and a written report you can act on. Use this list to compare proposals line by line.

Typical arc flash study deliverables, compiled from Zech Engineering and Electrical Reliability Services (Vertiv) deliverable lists and IEEE 1584.1-2022's scope. Checked November 26, 2026.
DeliverableWhat it gives you
Utility fault current confirmation18The starting point for every calculation
Validated one-line diagram18An accurate drawing of your system, useful long after the study
Short-circuit study and equipment duty evaluation18Which equipment, if any, is underrated for the available fault current
Protective device coordination study18Recommended settings so faults clear quickly and selectively
Incident energy calculations per IEEE 158418cal/cm² and arc flash boundary at each location21
PPE information and safe work practice recommendations21Inputs for your NFPA 70E program and energized work permits
Labels aligned with NFPA 70E and NEC 110.1618Field-ready equipment labels
Written report, PE-stamped where included18Assumptions, results and recommendations on record

Also ask for the native software model file. Without it, the next five-year update may start from scratch.

How long a study takes

Published estimates from engineering firms run from under two weeks to about four months, depending on facility size, equipment density and the condition of your records.

Arc flash study durations published by two US engineering firms (pages undated; checked November 26, 2026). Durations run from kickoff to final deliverables.
PublisherFacility describedPublished duration
Zech Engineering16"Most" studies2 to 6 weeks for most studies: data collection and scheduling 1 to 2 weeks, field survey 1 to 3 days, engineering and modeling 1 to 2 weeks, report, labels and review 3 to 5 days. Zech says small sites with clean records can finish in under two weeks and complex systems can take 6 to 8 weeks.
Herzig Engineering17150,000 to 300,000 sq ft9 to 16 weeks; longer with dense equipment and add-ons
Herzig Engineering17Example: 300,000 sq ft, medium equipment density, five utility transformersAbout 12 weeks

Field data collection comes early in both firms' timelines, and it depends on getting into the equipment. Feyen Zylstra notes that access can be limited by a lack of downtime23. If an insurer audit or contract sets your deadline, put the date in your request.

What a study costs

Published US budget ranges run from about $3,500 for a small, simple facility18 to $100,000 or more for large or complex sites19. For small facilities, two firms' tiers start at about $3,500 to $6,000 (Zech)18 and $7,500 to $15,000 for one or two buildings (Herzig)19. The main driver is how much equipment has to be modeled: Zech calls the number of buses "often the primary cost driver"18, and Leaf Electrical Safety says pricing follows the amount of electrical equipment, not building square footage20. Missing drawings, limited outage windows, labels and a PE stamp also move the price1823.

To compare every published range and try the per-bus estimator, see our arc flash study cost guide.

If the study finds high incident energy

When a location shows high incident energy, mitigation usually focuses on clearing the fault faster, because incident energy depends on how quickly the protective device isolates it6. OSHA's hierarchy of controls puts elimination, substitution and engineering controls ahead of administrative controls and PPE6.

  • Settings changes. The coordination study may show device settings that can be adjusted to clear faults faster. Ask the engineer to evaluate these before hardware changes.
  • Arc energy reduction on large breakers. NEC 240.87 calls for an arc energy reduction method on circuit breakers rated or adjustable to 1,200 A or higher1427. The 2014 and 2017 NEC text lists methods including zone-selective interlocking, differential relaying, energy-reducing maintenance switching, active arc flash mitigation systems and instantaneous trip set below the arcing current27; the list may differ in later editions, so check the edition your state enforces.
  • Maintenance. Herzig notes that maintenance affects how fast protective devices clear a fault, which affects incident energy3.

Ask whether the proposal includes mitigation recommendations, and whether re-running the model after changes costs extra.

How to choose a provider

Four kinds of firms do arc flash studies: independent engineering firms, independent testing companies, electrical contractors and equipment manufacturers' service groups. What matters is who does the engineering, who collects the field data and what's in the scope.

Engineering firms

Power system engineers who model and stamp studies. Ask whether they collect field data themselves or rely on you or a subcontractor.

NETA Accredited Companies

Third-party, independent firms for full-service testing, analysis and maintenance, which must be divested of competing service or manufacturing interests22. Useful when you want testing and the study from one firm.

Electrical contractors

Some electrical contractors also offer arc flash studies23. Ask who builds the model and who stamps the report.

Manufacturer service groups

Equipment makers' engineering services. NETA requires accredited companies to be divested of competing manufacturing interests22, so manufacturer service groups generally aren't NETA Accredited Companies; none of the four big manufacturers we checked were listed in NETA's directory in November 2026.

PE stamps and credentials

On engineer credentials: the OSHA and NFPA sources cited here don't name a professional engineer (PE) requirement for the study itself. Whether a stamp is legally required depends on your state's engineering rules, and your insurer, corporate standard or contract may require one. Zech lists a PE-stamped report among the deliverables a complete study may include, and notes that not all studies include one18.

Before you shortlist, use our arc flash proposal checklist to put every proposal against the same scope, and our credential checks to confirm NETA status, technician level and who stamps the report.

To see which national firms offer studies and how they differ, read our directory of arc flash study companies.

What to send for an accurate quote

A provider can price a study accurately once they know how much equipment is in scope and how good your existing data is. For the form, the first five items are enough; the rest helps once providers contact you.

  • Site ZIP code, facility type and the number of buildings in scope
  • Service voltage and the number of utility services or service transformers
  • Approximate count of switchboards, panelboards, MCCs and transformers (or buses, if you know)
  • Whether you have a one-line diagram, and how current it is
  • Date of your last study, the firm that did it and whether you have the model file
  • Generators, UPS systems, large motors or medium-voltage equipment
  • Outage windows, access limits and whether your electricians can assist
  • Deliverables you need: labels installed, PE stamp, mitigation options, training
  • Deadline and what drives it (insurer, audit, contract or five-year review)

Once a provider is chosen, expect requests for transformer nameplates, cable sizes and lengths, and breaker, fuse and relay settings. Feyen Zylstra says a missing or badly outdated one-line adds time, and that data collection, one-line updates and cable tracing can be done in-house to lower cost23.

Get quotes through Critical Power Index

Send one request and we'll review it. If we can match it with independent providers that serve your ZIP code and offer arc flash studies, we'll share it with up to three of them. Providers contact you directly to ask questions or quote, and you decide whether to hire anyone. It's free for facilities, and the full process is explained here. Providers may pay us a referral fee; see our referral disclosure. Critical Power Index is a referral service, not an engineering firm or contractor, and we don't perform or check the work.

Request arc flash study quotes

Sources

  1. NFPA 70E, Standard for Electrical Safety in the Workplace: standard development page, National Fire Protection Association. Current edition 2027; issued April 16, 2026, effective May 6, 2026. Checked 2026-11-26.
  2. NFPA 70E, 2027 edition: product page and summary of changes, National Fire Protection Association, 2026. Checked 2026-11-26.
  3. NFPA 70E 2027 changes explained, Herzig Engineering, October 30, 2026. Checked 2026-11-26.
  4. NFPA 70E correlating committee meeting agenda, 2027 revision cycle (equipment labeling and PPE selection text), National Fire Protection Association, December 2025. Committee document; confirm final wording in the published 2027 edition. Checked 2026-11-26.
  5. A better understanding of 70E, NFPA blog (Christopher Coache), August 4, 2022. Section numbers refer to the 2021 edition. Checked 2026-11-26.
  6. Protecting Employees from Electric-Arc Flash Hazards (OSHA 4472), Occupational Safety and Health Administration, 2024. Guidance document; creates no new legal obligations. Checked 2026-11-26.
  7. 29 CFR 1910.269, Electric power generation, transmission, and distribution, OSHA. See paragraph (l)(8). Checked 2026-11-26.
  8. 29 CFR 1910.335, Safeguards for personnel protection, OSHA. Checked 2026-11-26.
  9. IEEE 1584-2018, IEEE Guide for Performing Arc-Flash Hazard Calculations, IEEE Standards Association, November 30, 2018. Checked 2026-11-26.
  10. IEEE 1584.1-2022, Guide for the Specification of Scope and Deliverable Requirements for an Arc-Flash Hazard Calculation Study, IEEE Standards Association, July 12, 2022. Checked 2026-11-26.
  11. Introduction to the 2018 Edition of IEEE 1584 (presentation), IEEE Region 7 IAS/PES. Checked 2026-11-26.
  12. IEEE 1584-2018 changes offer a robust upgrade, Plant Engineering. Checked 2026-11-26.
  13. Arc flash warning label changes in the 2026 NEC, Daily Reporter (Mark Cook), November 25, 2026. Secondary summary; verify against the NFPA 70 text adopted in your jurisdiction. Checked 2026-11-26.
  14. NEC 240.87 arc energy reduction (catalog document), Schneider Electric. Checked 2026-11-26.
  15. Arc flash study process, Herzig Engineering. Checked 2026-11-26.
  16. How long does an arc flash study take?, Zech Engineering. Checked 2026-11-26.
  17. Arc flash study guide, Herzig Engineering. Checked 2026-11-26.
  18. Arc flash study cost, Zech Engineering. Checked 2026-11-26.
  19. Arc flash study cost estimate, Herzig Engineering, June 12, 2025 (modified June 14, 2026). Checked 2026-11-26.
  20. How much does an arc flash study cost?, Leaf Electrical Safety. Checked 2026-11-26.
  21. Arc flash studies, Electrical Reliability Services (Vertiv). Checked 2026-11-26.
  22. NETA accreditation overview, InterNational Electrical Testing Association. Checked 2026-11-26.
  23. Arc flash study, Feyen Zylstra, April 28, 2023 (modified). Checked 2026-11-26.
  24. NFPA 70B, Standard for Electrical Equipment Maintenance: standard development page, National Fire Protection Association. Current edition 2026; effective December 9, 2025. Checked 2026-11-26.
  25. NFPA 70B technical committee meeting minutes, 2026 revision cycle, National Fire Protection Association. Draft committee text; confirm final wording in the published edition. Checked 2026-11-26.
  26. Arc flash studies, UTEC. Checked 2026-11-26.
  27. NEC 240.87 arc energy reduction (code text, 2014 and 2017 editions), ElectricalLicenseRenewal.com. Secondary reproduction of older code text; check the NFPA 70 edition your jurisdiction enforces. Checked 2026-11-26.
  28. NFPA 70E second revision report, 2024 revision cycle (Section 130.7(C)(15), arc flash PPE category method), National Fire Protection Association. Committee text for the 2024 edition; confirm the table limits in the edition you apply. Checked 2026-11-26.
Request quotes