Published arc flash study price ranges
Six firms that sell arc flash studies publish prices: four give ranges by site size, one an average and one two project examples. Small sites run about $3,500 to $15,000; large, complex sites can pass $100,000.2513 The table lists every firm-published figure we found (we left out a forum estimate from about 2009), with the date each page shows and what each firm says its price covers. If you're still deciding whether you need a study at all, start with our arc flash study guide.
| Publisher and date | Small site | Medium site | Large or complex site | What the figure covers |
|---|---|---|---|---|
| Zech Engineering2 Undated; page title says "Real 2026 Pricing" | $3,500 to $6,000 | $6,000 to $14,000 | $14,000 to $22,000 or more | Broad budgeting ranges; final price depends on field verification, one-lines, coordination, labels and complexity |
| VB Engineering5 US pricing model, October 2026 | $4,500 to $9,000 (up to 25 buses) | $9,000 to $28,000 (26 to 100 buses) | $28,000 to $75,000 (101 to 300 buses); $75,000 and up above 300 buses | Engineering only, PE stamp included; field data, labels and boundary marking typically add 30 to 60 percent |
| Herzig Engineering1 June 12, 2025; updated June 14, 2026 | $7,500 to $15,000 (1 to 2 buildings) | $15,000 to $35,000 (campus or site) | $35,000 to $100,000+ | Typical ranges by facility size; varies with geography, access and existing documentation |
| Leaf Electrical Safety3 Undated | About $7,500 at the low end | $12,000 to $25,000 (Leaf's "small to medium") | $75,000 to $100,000; rare very large sites $100,000 to $500,000 or more | Ballpark for budgeting, adjusted for equipment density, drawings, access and in-house help |
| Feyen Zylstra4 Page modified April 28, 2023 | Most studies between $12,000 and $15,000 (the firm's average) | What this contractor sees across its own projects | ||
| e-Hazard6 September 14, 2021; updated January 2024 | Just under $3,000 (small multifamily renovation: one 208 V, 800 A panelboard feeding two metering boards and a few small house panels; the electrical contractor supplied the data and applied labels) | No example given | About $70,000 (food plant with its own 115 kV substation and a medium-voltage loop feeding 12 pad-mount transformers) | Two completed project examples, not ranges |
Each firm's own published figures; see the limits below.
The numbers disagree mainly because the firms aren't pricing the same scope. Zech Engineering says three quotes for one facility can range from $3,500 to $22,000 or more, and that this doesn't necessarily mean any firm is overpriced; it usually means they aren't pricing the same scope.2 VB's figures cover engineering only, with field work as add-ons, while Herzig and Leaf quote whole-facility ballparks.513 e-Hazard's single-panel example came in just under $3,000, below the published ranges, because the contractor collected the data and applied the labels.6
Estimate a budget from your bus count
Firms price either per facility (Herzig, Leaf, Zech) or per bus (VB), and either way the bus count sets the effort.1325 A bus is any point where the engineer calculates fault current and evaluates equipment, such as a switchboard, panelboard, motor control center, transformer or disconnect.2 Zech Engineering says a small commercial building may have 10 to 20 buses and a large industrial facility hundreds.2 Herzig puts a basic retail store at 30 to 50 pieces of equipment and a food processing plant in the hundreds.1
Arc flash study budget estimator
EstimatorCount the equipment that will be modeled. Each switchboard, panelboard, MCC, transformer secondary or fused disconnect is usually one bus.
Buses to model
–
Engineering at published per-bus rates
–
Indicative budget
–
Rates: VB Engineering's published US pricing (October 2026)5: about $140 per LV bus and $260 per MV bus, PE stamp included, $4,500 minimum; field data, labels and boundary marking add 30 to 60 percent. VB Engineering works outside the US too, and we have not confirmed its US engineering licensure. It calls these indicative, modeled rates, not prices from completed US projects. The tool counts each transformer as one low-voltage bus; VB prices a transformer primary as a medium-voltage bus, so enter MV primaries under medium-voltage buses. Below about 32 LV buses the tool shows VB's minimum fee; VB's own small-site band runs $4,500 to $9,000. Leaves out DC buses, buses above 15 kV, travel, multi-site work and VB's surcharge for outdated or missing one-lines (about 12 or 30 percent of the field phase).
Treat the result as a sanity check, not a budget line. We use VB Engineering's rates because it's the only firm we found that publishes modeled per-bus prices for US sites.5 VB Engineering works in several countries, and we have not confirmed its US engineering licensure. Its per-bus figures are what it calls indicative, modeled rates, not completed US project prices. Zech cautions that per-bus pricing can oversimplify scope, because a main switchboard with layered protective devices is more engineering than a simple distribution panel.2
What makes an arc flash study cost more or less
The amount of electrical equipment drives the price far more than floor area. Leaf Electrical Safety notes that a warehouse costs much less to study than a pulp and paper mill of the same size, because the mill has far more equipment.3 The table collects every driver the firms name, with any adjustment they publish.
| Driver | Effect on price | Source |
|---|---|---|
| Number of buses | Usually the main driver. Leaf adds 50 to 75 percent to a base estimate for equipment-dense sites and cuts about 50 percent for warehouse-style sites. | 23 |
| Voltage class | VB prices a medium-voltage bus at about $260 against about $140 for low voltage, because of relay settings, CT ratios and utility coordination. | 5 |
| Missing or outdated one-line | Leaf says no single-line adds roughly 25 to 35 percent. VB adds about 30 percent to its field phase for none and about 12 percent for outdated drawings. | 35 |
| Field verification | Checking breaker settings, nameplates, conductor sizes and transformer impedance on site adds effort. Studies built only on owner data cost less but rest on assumptions. | 2 |
| System complexity | Multiple sources, tie breakers, generators and alternate operating modes take longer to model than a simple radial system. | 2 |
| Access and downtime | Gear behind machinery, or gear that can only be opened during an outage, adds field time. Leaf's rule of thumb from mining: underground work costs 50 to 100 percent more. | 134 |
| Help from your electricians | Leaf cuts a base estimate 15 to 20 percent when in-house staff help collect data and trace circuits. Herzig warns that mistakes in that data lead to unsafe labels. | 31 |
| Labels, PE stamp and travel | Some quotes include printed labels and a PE-stamped report and some don't. Sites outside a firm's area may add travel. | 2 |
How to lower the cost without cutting scope
The levers that firms publish all reduce field time or rework, not the analysis itself.
- Have your electricians help. Leaf cuts its base estimate 15 to 20 percent when in-house staff collect data and trace circuits.3 Herzig warns that errors in owner-collected data lead to unsafe labels, so agree up front on who checks it.1
- Hand over a current one-line. A missing single-line adds roughly 25 to 35 percent in Leaf's estimate, and VB adds about 12 percent of its field phase for outdated drawings and about 30 percent for none.35
- Line up access and outages. Feyen Zylstra lists limited access, such as a lack of downtime, as a cost factor.4 If you already have a planned outage, ask whether field data collection can be scheduled into it.
- Update rather than start over. When VB holds an earlier model, it prices the reassessment per changed bus.5 Keep the native model file from any study you buy.
What a complete study includes, and what low quotes leave out
According to Zech Engineering, a complete study can include utility fault data, field-checked one-lines, short-circuit, coordination and incident energy calculations, labels and a PE-stamped report, and a lower quote may leave out field checks, coordination, labels or PE review.2 Zech's full list of what a complete study may include:
- Confirmation of available fault current from the utility
- Field-validated one-line diagrams
- Short-circuit study and an equipment duty evaluation
- Protective device coordination study
- Incident energy calculations per IEEE 1584
- Arc flash labels aligned with NFPA 70E and NEC 110.16
- A PE-stamped report
Not every project needs every item, Zech adds, but proposals should state their exclusions.2 IEEE 1584-2018 is still the active calculation standard. It covers three-phase AC systems from 208 V to 15 kV and doesn't cover single-phase AC or DC systems.10 If your site has UPS, battery or other DC equipment, ask how each quote handles it; VB, for example, prices DC buses as a separate line.5
According to Zech, a lower quote may assume any of the following:2
- Owner-supplied data only, with no field verification
- Software output without engineering review
- A limited equipment scope
- No coordination analysis
- No labels
- No PE review
A cheap study can cost more later
Herzig Engineering reports finding labels in the field that showed less than 4 cal/cm² where its corrected study found more than 50 cal/cm².1 A label that understates the hazard can lead a worker to wear the wrong PPE. Compare scope first and price second.
What an update or 5-year review costs
Firms say an update usually costs less than a first study when the original model and field data still exist,56 but we found no independent published dollar range for updates. NFPA 70E's labeling section (130.5, 2027 edition, per NFPA's December 2025 committee text) requires the data behind arc flash labels to be reviewed for accuracy at intervals not exceeding 5 years, and labels to be updated when a review finds a change that makes them inaccurate.813 The current edition is NFPA 70E-2027;9 confirm which edition your AHJ, insurer or contract enforces.
- A review isn't automatically a full recalculation. Zech Engineering describes it as deciding whether the existing analysis is still accurate, needs targeted updates or needs a rebuild.13
- One firm's figure. When VB Engineering holds the earlier model, it quotes the reassessment per changed bus and says it typically comes in well under half the first-study price.5 That's VB's claim about its own repeat work, not a market rate.
- Field verification still applies. In an April 2026 reply on its cost article, e-Hazard says its field verification regularly finds new or modified equipment even when clients report no changes.6
Three things can move an update quote: whether you can hand over the native software model rather than only the PDF report, how much of the system has changed, and which edition of IEEE 1584 the earlier study used (the 2018 edition superseded 2002).10 In the same reply on its cost article, an e-Hazard engineer notes that having the original model keeps engineering time low when little has changed, and that an unclear IEEE 1584 edition or an estimated utility contribution can add work.6
How long an arc flash study takes
Most studies take 2 to 6 weeks, according to Zech Engineering; large or poorly documented sites take longer, which also raises cost.7 See arc flash study timelines by site size.
How to compare arc flash study quotes
Compare prices only after you've confirmed the quotes cover the same work. Zech Engineering suggests asking whether each quote includes field verification, labels, updated one-lines, coordination and a PE stamp, and what it assumes and excludes.2 We'd also ask:
- Is field data collected by the firm, by your staff, or both?
- Are labels printed and installed, or delivered as a file?
- Which software is used, and will you receive the native model file?
- Which IEEE 1584 edition and which operating scenarios are modeled?
- Does the report include mitigation recommendations for high incident energy locations?
- Who signs the report, and in which state is that engineer licensed?
If the same firm will also collect field data or do maintenance testing, NETA accreditation is worth asking about. NETA accredits independent, third-party testing firms and requires them to be divested of competing service or manufacturing interests, so manufacturers' own service groups generally aren't NETA Accredited Companies.12 For a written request for proposal, IEEE 1584.1-2022 sets out the minimum scope and deliverables an owner should specify for a study.11
Who is qualified to perform an arc flash study?
In an April 2026 reply on its cost article, e-Hazard recommends that a licensed professional engineer with power systems experience perform or directly supervise the analysis, which it treats as engineering rather than electrical contracting.6 Zech notes that many contracts, insurers and jurisdictions require a PE-stamped report.2 For credentials and other checks, see how to choose an arc flash study provider.
What to send for an accurate quote
Providers can price a study faster and more tightly when they know your equipment count and the state of your drawings. Zech lists a rough bus count, facility type and size, whether one-lines are current, and whether you need a PE stamp and printed labels.2 Put the counts and answers in the form's details box. Providers will ask for drawings and any earlier study directly.
Three things move the price most, so include them in the form's details box:
- A rough count of switchboards, panelboards, MCCs, transformers and disconnects, or a bus count if you have one (the estimator above helps)
- Whether you have a one-line diagram and its date, or that it's missing or out of date
- The deliverables you need: coordination study, labels printed and installed, PE stamp, mitigation recommendations
Full checklist: what to send arc flash study providers. Then use the quote request form on this page.
Limits of these figures
Every dollar figure on this page is a firm's own published budgeting number or project example. None is a quote, an industry survey or a Critical Power Index estimate. Several pages are undated, and published prices can lag what firms charge today. The estimator uses one firm's modeled rates, and we haven't confirmed that firm's US licensure; it leaves out DC systems, buses above 15 kV, travel and multi-site work. Sites with multiple sources, substations or tight access limits can fall outside every range shown. This page isn't engineering advice, and you should confirm the NFPA 70E and NEC editions your AHJ enforces.
Get quotes through Critical Power Index
Send one request with your ZIP code and scope. We review it and, where we can find independent providers that serve your area and list arc flash studies, share it with up to three of them. Any provider that chooses to respond contacts you directly; we can't guarantee a response or a quote. It's free for facilities, and providers may pay us a referral fee (see the referral disclosure). Critical Power Index is a referral service, not an engineering firm or contractor, and you're never obligated to hire anyone. How the process works.
Request arc flash study quotes
More on arc flash studies and testing
- What an arc flash study involves and when NFPA 70E calls for one
- US companies that perform arc flash studies
- Acceptance and maintenance testing for switchgear, breakers and relays
- Switchgear maintenance intervals under NFPA 70B
Sources
- Arc Flash Study Cost Estimate: What Should You Expect?, Herzig Engineering, June 12, 2025 (updated June 14, 2026). Checked 2026-11-26.
- How Much Does an Arc Flash Study Cost?, Zech Engineering (Nick Zech, PE). Undated; page title references 2026 pricing. Checked 2026-11-26.
- How Much Does an Arc Flash Study Cost?, Leaf Electrical Safety. Undated. Checked 2026-11-26.
- Arc Flash Study, Feyen Zylstra, modified April 28, 2023. Checked 2026-11-26.
- Arc Flash Study Cost: Indicative Price per Bus, VB Engineering, pricing model dated October 2026. Vendor-published indicative, modeled pricing, not a quote. VB markets outside the US; its US licensure is not confirmed by us. Checked 2026-11-26.
- How Much Does an Arc Flash Study Cost?, e-Hazard (John Mason, PE), September 14, 2021 (updated January 2024). Includes an e-Hazard staff reply in the comments dated April 30, 2026. Checked 2026-11-26.
- How Long Does an Arc Flash Study Take?, Zech Engineering. Undated. Checked 2026-11-26.
- NEC Correlating Committee meeting agenda (NFPA 70E, 2027 edition cycle), National Fire Protection Association, December 2025. Committee text for Section 130.5 label and data review; not the issued standard. Checked 2026-11-26.
- NFPA 70E: Standard for Electrical Safety in the Workplace, document information, National Fire Protection Association. Current edition 2027, effective May 6, 2026. Checked 2026-11-26.
- IEEE 1584-2018: IEEE Guide for Performing Arc-Flash Hazard Calculations, IEEE Standards Association, November 30, 2018. Checked 2026-11-26.
- IEEE 1584.1-2022: Guide for the Specification of Scope and Deliverable Requirements for an Arc-Flash Hazard Calculation Study, IEEE Standards Association, July 12, 2022. Checked 2026-11-26.
- NETA Accreditation Overview, InterNational Electrical Testing Association. Checked 2026-11-26.
- When Should an Arc Flash Study Be Updated?, Zech Engineering. Undated. Cites the 2027 NFPA 70E labeling requirements at 130.5(H)(3) and (H)(4). Checked 2026-11-26.